What could be my risk mitigation strategies if my client wants to contract UAT?
.everyoneloves__top-leaderboard:empty,.everyoneloves__mid-leaderboard:empty,.everyoneloves__bot-mid-leaderboard:empty{ margin-bottom:0;
}
6
1
My client wants to squeeze UAT into 6 working days from originally planned 10 working days. This is because they want to go live because of an impending business reason. As a risk mitigation strategy I have proposed for 4 weeks of hypercare instead of general 2 weeks. I have also proposed for complete execution of UAT scripts within first 3 days of UAT and then to retest the defects along with the second iteration of execution in remaining 3 days. How else can I mitigate this risk?
risk-management testing quality