How do we improve the relationship with a client software team that performs poorly and is becoming less...





.everyoneloves__top-leaderboard:empty,.everyoneloves__mid-leaderboard:empty,.everyoneloves__bot-mid-leaderboard:empty{ margin-bottom:0;
}







51















I work as a team leader in a team of 6 (2 very senior devs, 1 senior dev, 1 medium level dev, 1 junior dev and 1 senior graphic designer). Our client has his own internal team of 5 (1 architect, 2 senior devs and 2 junior devs).



The performance and the skills of the internal team are extremely low (commits that don’t compile, even tags, merges that break/remove working functionalities and that reach production untested, nonsense questions, months to complete simple changes, etc.) and we are always fixing their poor work. For example:




  • We fixed dozens and dozens of bugs opened in the last year and a half and that were assigned to the internal team, spending less than 30 minutes on each (even in the part of the project we have never worked on before);

  • A project was assigned to the internal team and was estimated at 3 months: after 6 months they admitted they were unable to complete it, so the client assigned it to us. In 6 months they did less than 10% of the required work. In a month and a half we closed this project;

  • We had to spend more than a week to fix a mess in SVN they created


From the beginning of this year, the client more or less bypassed his own team and assigned everything directly to us (in fact our team will soon grow by at least 4 devs). The other team didn’t take it well and are trying to sabotage us; we need them to contact other suppliers because for their internal policy; 2 suppliers cannot speak directly without client mediation and they literally take weeks to simply forward an email. When we need clarifications on code they developed, they are elusive and don’t provide any useful explanation. They didn't give us resources or privileges that we required in order to complete our tasks, etc.



The client is well aware of the situation but he seems he wants to do nothing to solve it. Does anyone who went through a similar situation have some advice on how to solve this problem?










share|improve this question









New contributor




Elitot Confused is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
Check out our Code of Conduct.





















  • Maybe it will be useful to know the structure of client company. In my field there is a client (IT) who write details about the specifications and which we work with, but also there is a specialist division on client side (for who the software will be) which say "this task should be done, this not" and sort tasks according to priority. This division is authorized "above" both, the client IT and us. Is your client assimilable?

    – Allerleirauh
    Apr 5 at 7:18








  • 3





    @Allerleirauh client is a big (mainly national) company with more or less 2000 employees. This company has an internal IT department but is not its main focus (about 100 people) My company is multinational with 20000 employees. I work in the IT division. Your client is not assimilable with ours: internal IT decides autonomously the tasks that should be done, at what priority and who will develop them (internally, externally and to which supplier)

    – Elitot Confused
    Apr 5 at 12:08






  • 34





    Your company has 20,000 people? This is not something you should even attempt to manage yourself, as you are the team leader, not the one actually responsible for the contract. Tell your boss the issue; they will tell you what to do.

    – MineR
    Apr 5 at 13:50






  • 4





    By "the client is well aware of the situation" do you mean that you, your management, or whoever is in charge of the contract in your company, has communicated with the person or persons in the other company who are in charge of the contract and responsible for approving payment of your company's invoices? From other things you have said, it sounds like you mean "I sent email more than once to the people I normally communicate with on their team". If that's what you really mean, then that's not "the client is well aware of the situation".

    – Makyen
    Apr 5 at 15:32






  • 2





    You keep saying "client" but that doesn't tell us very much. What is your relationship with this other organisation? Are you a consultancy? For what purpose was your firm hired by the client?

    – Lightness Races in Orbit
    2 days ago


















51















I work as a team leader in a team of 6 (2 very senior devs, 1 senior dev, 1 medium level dev, 1 junior dev and 1 senior graphic designer). Our client has his own internal team of 5 (1 architect, 2 senior devs and 2 junior devs).



The performance and the skills of the internal team are extremely low (commits that don’t compile, even tags, merges that break/remove working functionalities and that reach production untested, nonsense questions, months to complete simple changes, etc.) and we are always fixing their poor work. For example:




  • We fixed dozens and dozens of bugs opened in the last year and a half and that were assigned to the internal team, spending less than 30 minutes on each (even in the part of the project we have never worked on before);

  • A project was assigned to the internal team and was estimated at 3 months: after 6 months they admitted they were unable to complete it, so the client assigned it to us. In 6 months they did less than 10% of the required work. In a month and a half we closed this project;

  • We had to spend more than a week to fix a mess in SVN they created


From the beginning of this year, the client more or less bypassed his own team and assigned everything directly to us (in fact our team will soon grow by at least 4 devs). The other team didn’t take it well and are trying to sabotage us; we need them to contact other suppliers because for their internal policy; 2 suppliers cannot speak directly without client mediation and they literally take weeks to simply forward an email. When we need clarifications on code they developed, they are elusive and don’t provide any useful explanation. They didn't give us resources or privileges that we required in order to complete our tasks, etc.



The client is well aware of the situation but he seems he wants to do nothing to solve it. Does anyone who went through a similar situation have some advice on how to solve this problem?










share|improve this question









New contributor




Elitot Confused is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
Check out our Code of Conduct.





















  • Maybe it will be useful to know the structure of client company. In my field there is a client (IT) who write details about the specifications and which we work with, but also there is a specialist division on client side (for who the software will be) which say "this task should be done, this not" and sort tasks according to priority. This division is authorized "above" both, the client IT and us. Is your client assimilable?

    – Allerleirauh
    Apr 5 at 7:18








  • 3





    @Allerleirauh client is a big (mainly national) company with more or less 2000 employees. This company has an internal IT department but is not its main focus (about 100 people) My company is multinational with 20000 employees. I work in the IT division. Your client is not assimilable with ours: internal IT decides autonomously the tasks that should be done, at what priority and who will develop them (internally, externally and to which supplier)

    – Elitot Confused
    Apr 5 at 12:08






  • 34





    Your company has 20,000 people? This is not something you should even attempt to manage yourself, as you are the team leader, not the one actually responsible for the contract. Tell your boss the issue; they will tell you what to do.

    – MineR
    Apr 5 at 13:50






  • 4





    By "the client is well aware of the situation" do you mean that you, your management, or whoever is in charge of the contract in your company, has communicated with the person or persons in the other company who are in charge of the contract and responsible for approving payment of your company's invoices? From other things you have said, it sounds like you mean "I sent email more than once to the people I normally communicate with on their team". If that's what you really mean, then that's not "the client is well aware of the situation".

    – Makyen
    Apr 5 at 15:32






  • 2





    You keep saying "client" but that doesn't tell us very much. What is your relationship with this other organisation? Are you a consultancy? For what purpose was your firm hired by the client?

    – Lightness Races in Orbit
    2 days ago














51












51








51


6






I work as a team leader in a team of 6 (2 very senior devs, 1 senior dev, 1 medium level dev, 1 junior dev and 1 senior graphic designer). Our client has his own internal team of 5 (1 architect, 2 senior devs and 2 junior devs).



The performance and the skills of the internal team are extremely low (commits that don’t compile, even tags, merges that break/remove working functionalities and that reach production untested, nonsense questions, months to complete simple changes, etc.) and we are always fixing their poor work. For example:




  • We fixed dozens and dozens of bugs opened in the last year and a half and that were assigned to the internal team, spending less than 30 minutes on each (even in the part of the project we have never worked on before);

  • A project was assigned to the internal team and was estimated at 3 months: after 6 months they admitted they were unable to complete it, so the client assigned it to us. In 6 months they did less than 10% of the required work. In a month and a half we closed this project;

  • We had to spend more than a week to fix a mess in SVN they created


From the beginning of this year, the client more or less bypassed his own team and assigned everything directly to us (in fact our team will soon grow by at least 4 devs). The other team didn’t take it well and are trying to sabotage us; we need them to contact other suppliers because for their internal policy; 2 suppliers cannot speak directly without client mediation and they literally take weeks to simply forward an email. When we need clarifications on code they developed, they are elusive and don’t provide any useful explanation. They didn't give us resources or privileges that we required in order to complete our tasks, etc.



The client is well aware of the situation but he seems he wants to do nothing to solve it. Does anyone who went through a similar situation have some advice on how to solve this problem?










share|improve this question









New contributor




Elitot Confused is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
Check out our Code of Conduct.












I work as a team leader in a team of 6 (2 very senior devs, 1 senior dev, 1 medium level dev, 1 junior dev and 1 senior graphic designer). Our client has his own internal team of 5 (1 architect, 2 senior devs and 2 junior devs).



The performance and the skills of the internal team are extremely low (commits that don’t compile, even tags, merges that break/remove working functionalities and that reach production untested, nonsense questions, months to complete simple changes, etc.) and we are always fixing their poor work. For example:




  • We fixed dozens and dozens of bugs opened in the last year and a half and that were assigned to the internal team, spending less than 30 minutes on each (even in the part of the project we have never worked on before);

  • A project was assigned to the internal team and was estimated at 3 months: after 6 months they admitted they were unable to complete it, so the client assigned it to us. In 6 months they did less than 10% of the required work. In a month and a half we closed this project;

  • We had to spend more than a week to fix a mess in SVN they created


From the beginning of this year, the client more or less bypassed his own team and assigned everything directly to us (in fact our team will soon grow by at least 4 devs). The other team didn’t take it well and are trying to sabotage us; we need them to contact other suppliers because for their internal policy; 2 suppliers cannot speak directly without client mediation and they literally take weeks to simply forward an email. When we need clarifications on code they developed, they are elusive and don’t provide any useful explanation. They didn't give us resources or privileges that we required in order to complete our tasks, etc.



The client is well aware of the situation but he seems he wants to do nothing to solve it. Does anyone who went through a similar situation have some advice on how to solve this problem?







performance clients






share|improve this question









New contributor




Elitot Confused is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
Check out our Code of Conduct.











share|improve this question









New contributor




Elitot Confused is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
Check out our Code of Conduct.









share|improve this question




share|improve this question








edited 2 days ago









Nathan L

63739




63739






New contributor




Elitot Confused is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
Check out our Code of Conduct.









asked Apr 5 at 6:54









Elitot ConfusedElitot Confused

267125




267125




New contributor




Elitot Confused is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
Check out our Code of Conduct.





New contributor





Elitot Confused is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
Check out our Code of Conduct.






Elitot Confused is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
Check out our Code of Conduct.













  • Maybe it will be useful to know the structure of client company. In my field there is a client (IT) who write details about the specifications and which we work with, but also there is a specialist division on client side (for who the software will be) which say "this task should be done, this not" and sort tasks according to priority. This division is authorized "above" both, the client IT and us. Is your client assimilable?

    – Allerleirauh
    Apr 5 at 7:18








  • 3





    @Allerleirauh client is a big (mainly national) company with more or less 2000 employees. This company has an internal IT department but is not its main focus (about 100 people) My company is multinational with 20000 employees. I work in the IT division. Your client is not assimilable with ours: internal IT decides autonomously the tasks that should be done, at what priority and who will develop them (internally, externally and to which supplier)

    – Elitot Confused
    Apr 5 at 12:08






  • 34





    Your company has 20,000 people? This is not something you should even attempt to manage yourself, as you are the team leader, not the one actually responsible for the contract. Tell your boss the issue; they will tell you what to do.

    – MineR
    Apr 5 at 13:50






  • 4





    By "the client is well aware of the situation" do you mean that you, your management, or whoever is in charge of the contract in your company, has communicated with the person or persons in the other company who are in charge of the contract and responsible for approving payment of your company's invoices? From other things you have said, it sounds like you mean "I sent email more than once to the people I normally communicate with on their team". If that's what you really mean, then that's not "the client is well aware of the situation".

    – Makyen
    Apr 5 at 15:32






  • 2





    You keep saying "client" but that doesn't tell us very much. What is your relationship with this other organisation? Are you a consultancy? For what purpose was your firm hired by the client?

    – Lightness Races in Orbit
    2 days ago



















  • Maybe it will be useful to know the structure of client company. In my field there is a client (IT) who write details about the specifications and which we work with, but also there is a specialist division on client side (for who the software will be) which say "this task should be done, this not" and sort tasks according to priority. This division is authorized "above" both, the client IT and us. Is your client assimilable?

    – Allerleirauh
    Apr 5 at 7:18








  • 3





    @Allerleirauh client is a big (mainly national) company with more or less 2000 employees. This company has an internal IT department but is not its main focus (about 100 people) My company is multinational with 20000 employees. I work in the IT division. Your client is not assimilable with ours: internal IT decides autonomously the tasks that should be done, at what priority and who will develop them (internally, externally and to which supplier)

    – Elitot Confused
    Apr 5 at 12:08






  • 34





    Your company has 20,000 people? This is not something you should even attempt to manage yourself, as you are the team leader, not the one actually responsible for the contract. Tell your boss the issue; they will tell you what to do.

    – MineR
    Apr 5 at 13:50






  • 4





    By "the client is well aware of the situation" do you mean that you, your management, or whoever is in charge of the contract in your company, has communicated with the person or persons in the other company who are in charge of the contract and responsible for approving payment of your company's invoices? From other things you have said, it sounds like you mean "I sent email more than once to the people I normally communicate with on their team". If that's what you really mean, then that's not "the client is well aware of the situation".

    – Makyen
    Apr 5 at 15:32






  • 2





    You keep saying "client" but that doesn't tell us very much. What is your relationship with this other organisation? Are you a consultancy? For what purpose was your firm hired by the client?

    – Lightness Races in Orbit
    2 days ago

















Maybe it will be useful to know the structure of client company. In my field there is a client (IT) who write details about the specifications and which we work with, but also there is a specialist division on client side (for who the software will be) which say "this task should be done, this not" and sort tasks according to priority. This division is authorized "above" both, the client IT and us. Is your client assimilable?

– Allerleirauh
Apr 5 at 7:18







Maybe it will be useful to know the structure of client company. In my field there is a client (IT) who write details about the specifications and which we work with, but also there is a specialist division on client side (for who the software will be) which say "this task should be done, this not" and sort tasks according to priority. This division is authorized "above" both, the client IT and us. Is your client assimilable?

– Allerleirauh
Apr 5 at 7:18






3




3





@Allerleirauh client is a big (mainly national) company with more or less 2000 employees. This company has an internal IT department but is not its main focus (about 100 people) My company is multinational with 20000 employees. I work in the IT division. Your client is not assimilable with ours: internal IT decides autonomously the tasks that should be done, at what priority and who will develop them (internally, externally and to which supplier)

– Elitot Confused
Apr 5 at 12:08





@Allerleirauh client is a big (mainly national) company with more or less 2000 employees. This company has an internal IT department but is not its main focus (about 100 people) My company is multinational with 20000 employees. I work in the IT division. Your client is not assimilable with ours: internal IT decides autonomously the tasks that should be done, at what priority and who will develop them (internally, externally and to which supplier)

– Elitot Confused
Apr 5 at 12:08




34




34





Your company has 20,000 people? This is not something you should even attempt to manage yourself, as you are the team leader, not the one actually responsible for the contract. Tell your boss the issue; they will tell you what to do.

– MineR
Apr 5 at 13:50





Your company has 20,000 people? This is not something you should even attempt to manage yourself, as you are the team leader, not the one actually responsible for the contract. Tell your boss the issue; they will tell you what to do.

– MineR
Apr 5 at 13:50




4




4





By "the client is well aware of the situation" do you mean that you, your management, or whoever is in charge of the contract in your company, has communicated with the person or persons in the other company who are in charge of the contract and responsible for approving payment of your company's invoices? From other things you have said, it sounds like you mean "I sent email more than once to the people I normally communicate with on their team". If that's what you really mean, then that's not "the client is well aware of the situation".

– Makyen
Apr 5 at 15:32





By "the client is well aware of the situation" do you mean that you, your management, or whoever is in charge of the contract in your company, has communicated with the person or persons in the other company who are in charge of the contract and responsible for approving payment of your company's invoices? From other things you have said, it sounds like you mean "I sent email more than once to the people I normally communicate with on their team". If that's what you really mean, then that's not "the client is well aware of the situation".

– Makyen
Apr 5 at 15:32




2




2





You keep saying "client" but that doesn't tell us very much. What is your relationship with this other organisation? Are you a consultancy? For what purpose was your firm hired by the client?

– Lightness Races in Orbit
2 days ago





You keep saying "client" but that doesn't tell us very much. What is your relationship with this other organisation? Are you a consultancy? For what purpose was your firm hired by the client?

– Lightness Races in Orbit
2 days ago










11 Answers
11






active

oldest

votes


















140














Please don't mislead yourself, you are nothing more than an external contractor to the company. You are NOT part of the company, so there is no legal or moral reason to grant you anything more than you already have. You don't belong to the company, you are not their human resources, you work as a provider-client relationship.



You have been paid, right? There should not be any reason for you to go above the boundary, it's not your company. Please don't be emotional. If you're not given resources, simply ask. If not granted, it's not yours.




Someone that pass through a similar situation has some advice on how to solve this problem?




Simple. Send your invoice to your client for your time.






share|improve this answer


























  • Comments are not for extended discussion; this conversation has been moved to chat.

    – Monica Cellio
    yesterday











  • I agree with this answer, also worth mentioning: if you don't like it, move on and get a contract you enjoy.

    – SaggingRufus
    17 hours ago



















57














This is normal. The client doesn't have a good development team, so they contract some of the work to you. Their development team realise that you are a threat to their jobs so they have no incentive to help you.



Their manager should have been aware that this was going to happen, and there are various things he can do to solve it, but that's not your problem.



Your problem is how to ensure that these delays don't make you look bad to the person paying the bill. Make sure he's aware that there are problems and ask how you can help him.



Maybe he'd like to know about email queries that are unanswered after a week, or maybe he'd like to be CC'd at the start. Maybe he'd like you to fix the other team's bugs and just bill him, but maybe he wants to approve each one.






share|improve this answer



















  • 11





    Presumably there are formal contacts for the outsource company and the client company. Problems should be escalated to that level. The IT company should give regular feedback from that level. We completely X, and Y. Z will be completed in 3 weeks. "Elitot Confused" has been waiting two weeks for aaa so we do not have an estimated completion date for AAA. "Elitot Confused" has been waiting five weeks fo bbb and so we have stopped work on BBB. and so on. // Short version - Document everything!!!

    – MaxW
    Apr 5 at 17:55








  • 2





    Yes, "document everything" was the phrase I was looking for somewhere in these answers. That's the most important thing.

    – Dannie
    yesterday






  • 2





    @MaxW -- Your comment would make a good answer.

    – Jasper
    yesterday



















27














Email the requests to the client team, and follow up with an email after the amount of time it would have taken you to comply with that request. CC this (nicely worded) reminder to the boss of the client company. They will either ignore it or help you out. If they ignore it, you have the paper trail to prove you are not the ones slowing the project, if they help you, all the better. After some iterations the boss of the client company will think of a way to reduce his spam-load, and give you a quick pass through (Some person just passing along the messages, as your own personal VPN).



In parallel, try to establish a personal relationship with one or more members of the other team. The petty communication outages that they produce are a sign that they harbor personal resentment. This can often be remedied by face-to-face meet ups. I stress personal relationships. Not the 'let's implement X'-kind of conversation, but the 'public transport sure sucks, huh?'-common ground kind of conversation. Let them see the humans in your bunch of know-it-alls , and try yourself to see the humans in their bunch of nitwits.






share|improve this answer


























  • Knowing the client, they will ignore the spam. We had a lot of chats and meeting with person of that team. Usually they stay on their ideas and we stay on ours. usually again ours proves to be correct and the client knows it (because we use solid proof to demonstrate our ideas)

    – Elitot Confused
    Apr 5 at 12:18






  • 3





    @ElitotConfused If they ignore the spam, you will have a BS job, but a paid BS job - find the mental place to deal with that, or quit; --- about the meetups: I stress personal relationships. Not the 'let's implement X'-kind of conversation, but the 'public transport sure sucks, huh?' kind of conversation. Let them see the humans in your bunch of know-it-alls , and try yourself to see the humans in their bunch of nitwits.

    – bukwyrm
    Apr 5 at 12:48



















12















Client is well aware of the situation but he seems he wants to do
nothing to solve.




So, you've brought this to the attention of the "powers that be" and they're not interested in fixing the problem. I assume that they pay you for all of this "extra" work that you perform? If so, then either continue performing the work and continue getting paid for it or fire the client. There are no other options.






share|improve this answer



















  • 1





    this is not helpful if for example boss of own company and boss of client insist on this relationship...

    – Allerleirauh
    Apr 5 at 7:41






  • 2





    @Allerleirauh "there are no other options" may not be helpful but it is the right answer

    – Pierre Arlaud
    Apr 5 at 12:02






  • 1





    We work on a body rental type of contract. There is no extra pay. the price is fixed at the beginning of the contract.

    – Elitot Confused
    Apr 5 at 12:23






  • 3





    @ElitotConfused I understand you saying that the cost per hour is fixed, but is the number of hours fixed or the product delivered (or both)? If it is both, you should find a new job. Otherwise, the cost has been increased--either they are paying for more hours (overtime) or they are paying for more hours (because it will take longer to get their product delivered).

    – user3067860
    Apr 5 at 18:33



















6














Ask for a regular status meeting with the client (hopefully you have that already but I get the sense that you don't). (NOTE: By regular I mean at least weekly, if not 2-3 times a week. If you can swing it, a stand up every day would be ideal.) During this status meeting, talk about the roadblocks you currently have... list them one by one, what you need, what you are waiting for and from whom, and what the dangers are if the request isn't filled in a timely manner... the project quality will suffer, you will ship late, etc.




We sent an email last week that we need X from the suppliers and that we would need it within a week in order to not put the project deadline in danger. We are rapidly approaching a week since our request. Do you have any updates on when we might get X? If we don't get it by this Friday, we will have to push back the delivery date by a week.



We sent an email last week to Jim asking for clarification on the Widget code. We can't proceed until we get that clarification. When can we set up that meeting?




and so on. Don't be accusatory or emotional, be factual, be clear about what problems this issue is causing or will cause to the project. When you don't get X for 3 weeks and you needed it the next day, no one should be surprised when you state that the delivery date will slip by 3 weeks.



Once things start looking like you won't ship on the initially agreed upon time, start communicating regularly with the client management. Inform them that the X, Y, and Z delays that you have notified them of are of their teams' doing and will put you past the scheduled timeframe. Any additional work past X date will incur additional at the rate of $Z. (Maybe it's too late to do some of this but you can at least start dropping hints of contract renegotiation due to delays beyond your control and of the client company's making).






share|improve this answer



















  • 2





    Yup. Status meeting should have the Joe Friday approach. "Just the facts sir..." It is not a place to brainstorm solutions. So the client contact takes a todo to have Joe at client's site respond or to find out when Joe will respond.

    – MaxW
    Apr 5 at 18:03



















3














Here is what I read:




  • We are great

  • Client not so much

  • They don't like us


Pro-tip, sometimes it better to be liked than right. Who do you want to be friends with more, the boss man, or the workers? Boss man pays the bills so always be his friend. But sometimes it helps to be friends with the workers also.



So instead of "Us" versus "Them", try to make it "We".



Rule #1: BE NICE



I'm sure you are always very professional, but from what you said in your post, I'm doubting you are always nice.



Sometimes a friendly visit to the client, box of donuts/candy/meat-veg tray/ice cream/movie tickets/etc... can go along way. Basically say, "we want to get along, we want to help you, we are on your side."



This isn't so much a reward, since it doesn't sound like you are in a position to reward or punish. Its more about trying to change the perception of the other team about you from "they are our enemies" to "they are our friends".



Rule #2: Be in control



If I was manager in this situation, I would say, "how can we manage the code better".



If possible, I'd maintain a separate Git repo, where you can add their contributions as separate pull requests. If they are stuck on SVN, so be it. You can give them your contributions as big single commits. Even if you have to move the code manually, its better than the client team screwing up the repo your team depends on.



Don't let their bad commits and bad SVN practices control your productivity.



Also, like the other posts said, document communications in case you need to CYA.



Good luck!






share|improve this answer










New contributor




Turtle1363 is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
Check out our Code of Conduct.
















  • 3





    Seriously? You're suggesting to reward obstructionist and unprofessional behaviour by buying another company's employees .. ice cream and movie tickets?

    – Lightness Races in Orbit
    2 days ago













  • And SVN is not the problem here.

    – Lightness Races in Orbit
    2 days ago











  • @LightnessRacesinOrbit sometimes the carrot works better than the stick. It’s not about “rewarding” so much as strategies for controlling the situation to obtain the desired outcome.

    – Turtle1363
    2 days ago








  • 4





    If I were wilfully ignoring a team for weeks on end, then they turned up to give me movie tickets, I'd find that really awkward and weird.

    – Lightness Races in Orbit
    2 days ago






  • 2





    @LightnessRacesinOrbit, maybe? Relationships can be awkward and weird. That's when you pull the team lead aside and say something to the effect of, "I feel like our communication hasn't been the best lately. I want you to know that we are here for you, and we all have the same goal of wanting the company to succeed. I just wanted to give you this small token, I hope you enjoy it. If you need anything please let us know. We are looking forward to the new challenges and opportunities in the next few weeks, I hope I can count on you for your support."

    – Turtle1363
    2 days ago



















2














Document each request, each complaint, and the hours wasted trying to work through the internal team to get the resources you need.



Right now, the internal team is fighting you because, so far, you have proven more capable of handling the application and are upstaging them - they are retaliating by making things more difficult for you.



Continue to provide the support you have thus far, and keep your client in the loop about all of these hang-ups. CC them, if you can, so that they are well aware of your attempts to keep things moving.



Eventually, they will have to confront this issue - but this is not your problem to solve. Your only concern should be getting your own work done, and showing that you are doing everything you can to get the resources for that work.



So long as you are doing your work to the degree you've described thus far, with the only complications being the internal team, they should have no reason to break off ties with you (though, they may want to consider restructuring that team - but again, this is not your problem to solve).






share|improve this answer
























  • +1 this seems the right answer. An excel sheet with emails and how long they are delayed, can go a long way.

    – Rui F Ribeiro
    2 days ago



















1














Where is the client internal team located? Is there a possibility that somebody from your team can go to the site where the internal team is located? I have had experiences in the past with teams that were difficult to work with, and I find that the best solution is to just go down and talk with people directly. I have had to spend entire days tracking down information myself from internal teams, just because the communication and initiative was simply not there. There is no need to be abrasive, or confrontational, just show up and get the communication lines established. Find out if they have a weekly meeting and have someone attend it. The bottom line is that the other team is struggling and your work is showing that to everyone. They are defensive for a good reason, so just show up with the attitude of "how can we help each other?". Maybe you can start doing some mentoring, or help them improve their process. You are hired as consultants not just to deliver the project, but to enhance the company/team.






share|improve this answer








New contributor




Brian Y is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
Check out our Code of Conduct.




























    0














    So I've read the existing answers and there's more to deal with.




    Send your invoice to your client for your time.




    Correct; however we also now have an employee morale problem on your side; or if we don't we will soon. Whatever cheapish things you can do to keep morale up, it's time to start doing them.



    You may have to approach your customer with something along the lines of "Due to certain problems on your side causing an employee morale problem for us, we have to increase our future rates for you by about 10% so that we can buy perks for the employees." But please, find somebody more diplomatic than I.






    share|improve this answer



















    • 2





      OP is not the boss, so I don't think this answer makes sense for them.

      – user87779
      Apr 5 at 20:03











    • @user87779: In which case the morale problem will have to propagate upwards until it does reach someone who can act on it.

      – Joshua
      Apr 5 at 21:52











    • exactly, i agree. So maybe edit the answer to say that, and maybe a way for the OP to help if happen if you think they can.

      – user87779
      Apr 5 at 21:55













    • @user87779: I don't suppose you could splice an edit in? I've ran out of ability (which is why my rep stays low...)

      – Joshua
      Apr 5 at 23:04











    • huh, I'm not able to either. I wonder if the question was protected or something weird.

      – user87779
      Apr 6 at 0:34



















    0














    Other answers covered how to cover the financial side of the things. Now, if their damage also causes you unnecessary anxiety and setbacks that extra money alone can't fix, you can eliminate that damage alone. For example, with these measures:




    • Don't work on the same codebase. Only merge their changes occasionally (to drastically limit the time spent on pointing out their flaws again and again) and only after they pass your scrunity.


      • You can rationalize this to the client as smth like: "Their code is not up to our standards so we have to bring it up to them each time before incorporating it -- otherwise, it costs much more of our time and your money down the line".

      • Incentivise them to merge your changes back opportunistically by smth like: "Otherwise, it will cost us disproportionally more time on the next merge."

      • You mentioned that they are using SVN. You can use Git internally 'cuz it features much more advanced branching and merging logic, making complex merges much easier. (Git comes with a two-way SVN bridge out of the box.)



    • Don't fix their bugs for them as an integral part of your work but rather as a separate activity (e.g. as a part of the above-mentioned scrunity) so that it's easy to separate it from your regular work and easy to bill for it separately (plus the client will see exactly how much their staff's incompetence is costing them).

    • If your part of the work depends on some modules provided by them, warn the client that you will not complete that part of functionality if their module doesn't arrive in time. Only work on that module once the client explicitly asks you to and in the same manner as above.

    • Offer to coach their staff as an extra activity but only if they themselves are willing -- from code reviews (e.g. during the above scrunity, let them themselves address the flaws) to teaching them the best practices.






    share|improve this answer

































      -1














      The customer (here: the client) is always right. As long as the customer pays. So as long as the customer pays for every hour you work, it doesn’t matter if their team is lazy and incompetent. If your job takes three times longer, you get paid three times as much.



      Of course, as long as the customer pays. So you should have a log about anything you asked the client team to do, and when it was delivered, and with ho many bugs. So if the customer doesn’t want to pay, you can show them why things take so long.






      share|improve this answer



















      • 1





        The OP has said they get a fixed amount of money. I don't know exactly what that entails, but in a few other comments they seem to imply they don't get paid more for working longer. That seems crazy to me, but you may know more about situations like that.

        – user87779
        Apr 5 at 22:27












      protected by mcknz yesterday



      Thank you for your interest in this question.
      Because it has attracted low-quality or spam answers that had to be removed, posting an answer now requires 10 reputation on this site (the association bonus does not count).



      Would you like to answer one of these unanswered questions instead?














      11 Answers
      11






      active

      oldest

      votes








      11 Answers
      11






      active

      oldest

      votes









      active

      oldest

      votes






      active

      oldest

      votes









      140














      Please don't mislead yourself, you are nothing more than an external contractor to the company. You are NOT part of the company, so there is no legal or moral reason to grant you anything more than you already have. You don't belong to the company, you are not their human resources, you work as a provider-client relationship.



      You have been paid, right? There should not be any reason for you to go above the boundary, it's not your company. Please don't be emotional. If you're not given resources, simply ask. If not granted, it's not yours.




      Someone that pass through a similar situation has some advice on how to solve this problem?




      Simple. Send your invoice to your client for your time.






      share|improve this answer


























      • Comments are not for extended discussion; this conversation has been moved to chat.

        – Monica Cellio
        yesterday











      • I agree with this answer, also worth mentioning: if you don't like it, move on and get a contract you enjoy.

        – SaggingRufus
        17 hours ago
















      140














      Please don't mislead yourself, you are nothing more than an external contractor to the company. You are NOT part of the company, so there is no legal or moral reason to grant you anything more than you already have. You don't belong to the company, you are not their human resources, you work as a provider-client relationship.



      You have been paid, right? There should not be any reason for you to go above the boundary, it's not your company. Please don't be emotional. If you're not given resources, simply ask. If not granted, it's not yours.




      Someone that pass through a similar situation has some advice on how to solve this problem?




      Simple. Send your invoice to your client for your time.






      share|improve this answer


























      • Comments are not for extended discussion; this conversation has been moved to chat.

        – Monica Cellio
        yesterday











      • I agree with this answer, also worth mentioning: if you don't like it, move on and get a contract you enjoy.

        – SaggingRufus
        17 hours ago














      140












      140








      140







      Please don't mislead yourself, you are nothing more than an external contractor to the company. You are NOT part of the company, so there is no legal or moral reason to grant you anything more than you already have. You don't belong to the company, you are not their human resources, you work as a provider-client relationship.



      You have been paid, right? There should not be any reason for you to go above the boundary, it's not your company. Please don't be emotional. If you're not given resources, simply ask. If not granted, it's not yours.




      Someone that pass through a similar situation has some advice on how to solve this problem?




      Simple. Send your invoice to your client for your time.






      share|improve this answer















      Please don't mislead yourself, you are nothing more than an external contractor to the company. You are NOT part of the company, so there is no legal or moral reason to grant you anything more than you already have. You don't belong to the company, you are not their human resources, you work as a provider-client relationship.



      You have been paid, right? There should not be any reason for you to go above the boundary, it's not your company. Please don't be emotional. If you're not given resources, simply ask. If not granted, it's not yours.




      Someone that pass through a similar situation has some advice on how to solve this problem?




      Simple. Send your invoice to your client for your time.







      share|improve this answer














      share|improve this answer



      share|improve this answer








      edited Apr 5 at 15:00









      AndreiROM

      46k23108178




      46k23108178










      answered Apr 5 at 8:10









      SmallChessSmallChess

      1,6815924




      1,6815924













      • Comments are not for extended discussion; this conversation has been moved to chat.

        – Monica Cellio
        yesterday











      • I agree with this answer, also worth mentioning: if you don't like it, move on and get a contract you enjoy.

        – SaggingRufus
        17 hours ago



















      • Comments are not for extended discussion; this conversation has been moved to chat.

        – Monica Cellio
        yesterday











      • I agree with this answer, also worth mentioning: if you don't like it, move on and get a contract you enjoy.

        – SaggingRufus
        17 hours ago

















      Comments are not for extended discussion; this conversation has been moved to chat.

      – Monica Cellio
      yesterday





      Comments are not for extended discussion; this conversation has been moved to chat.

      – Monica Cellio
      yesterday













      I agree with this answer, also worth mentioning: if you don't like it, move on and get a contract you enjoy.

      – SaggingRufus
      17 hours ago





      I agree with this answer, also worth mentioning: if you don't like it, move on and get a contract you enjoy.

      – SaggingRufus
      17 hours ago













      57














      This is normal. The client doesn't have a good development team, so they contract some of the work to you. Their development team realise that you are a threat to their jobs so they have no incentive to help you.



      Their manager should have been aware that this was going to happen, and there are various things he can do to solve it, but that's not your problem.



      Your problem is how to ensure that these delays don't make you look bad to the person paying the bill. Make sure he's aware that there are problems and ask how you can help him.



      Maybe he'd like to know about email queries that are unanswered after a week, or maybe he'd like to be CC'd at the start. Maybe he'd like you to fix the other team's bugs and just bill him, but maybe he wants to approve each one.






      share|improve this answer



















      • 11





        Presumably there are formal contacts for the outsource company and the client company. Problems should be escalated to that level. The IT company should give regular feedback from that level. We completely X, and Y. Z will be completed in 3 weeks. "Elitot Confused" has been waiting two weeks for aaa so we do not have an estimated completion date for AAA. "Elitot Confused" has been waiting five weeks fo bbb and so we have stopped work on BBB. and so on. // Short version - Document everything!!!

        – MaxW
        Apr 5 at 17:55








      • 2





        Yes, "document everything" was the phrase I was looking for somewhere in these answers. That's the most important thing.

        – Dannie
        yesterday






      • 2





        @MaxW -- Your comment would make a good answer.

        – Jasper
        yesterday
















      57














      This is normal. The client doesn't have a good development team, so they contract some of the work to you. Their development team realise that you are a threat to their jobs so they have no incentive to help you.



      Their manager should have been aware that this was going to happen, and there are various things he can do to solve it, but that's not your problem.



      Your problem is how to ensure that these delays don't make you look bad to the person paying the bill. Make sure he's aware that there are problems and ask how you can help him.



      Maybe he'd like to know about email queries that are unanswered after a week, or maybe he'd like to be CC'd at the start. Maybe he'd like you to fix the other team's bugs and just bill him, but maybe he wants to approve each one.






      share|improve this answer



















      • 11





        Presumably there are formal contacts for the outsource company and the client company. Problems should be escalated to that level. The IT company should give regular feedback from that level. We completely X, and Y. Z will be completed in 3 weeks. "Elitot Confused" has been waiting two weeks for aaa so we do not have an estimated completion date for AAA. "Elitot Confused" has been waiting five weeks fo bbb and so we have stopped work on BBB. and so on. // Short version - Document everything!!!

        – MaxW
        Apr 5 at 17:55








      • 2





        Yes, "document everything" was the phrase I was looking for somewhere in these answers. That's the most important thing.

        – Dannie
        yesterday






      • 2





        @MaxW -- Your comment would make a good answer.

        – Jasper
        yesterday














      57












      57








      57







      This is normal. The client doesn't have a good development team, so they contract some of the work to you. Their development team realise that you are a threat to their jobs so they have no incentive to help you.



      Their manager should have been aware that this was going to happen, and there are various things he can do to solve it, but that's not your problem.



      Your problem is how to ensure that these delays don't make you look bad to the person paying the bill. Make sure he's aware that there are problems and ask how you can help him.



      Maybe he'd like to know about email queries that are unanswered after a week, or maybe he'd like to be CC'd at the start. Maybe he'd like you to fix the other team's bugs and just bill him, but maybe he wants to approve each one.






      share|improve this answer













      This is normal. The client doesn't have a good development team, so they contract some of the work to you. Their development team realise that you are a threat to their jobs so they have no incentive to help you.



      Their manager should have been aware that this was going to happen, and there are various things he can do to solve it, but that's not your problem.



      Your problem is how to ensure that these delays don't make you look bad to the person paying the bill. Make sure he's aware that there are problems and ask how you can help him.



      Maybe he'd like to know about email queries that are unanswered after a week, or maybe he'd like to be CC'd at the start. Maybe he'd like you to fix the other team's bugs and just bill him, but maybe he wants to approve each one.







      share|improve this answer












      share|improve this answer



      share|improve this answer










      answered Apr 5 at 12:19









      Robin BennettRobin Bennett

      82126




      82126








      • 11





        Presumably there are formal contacts for the outsource company and the client company. Problems should be escalated to that level. The IT company should give regular feedback from that level. We completely X, and Y. Z will be completed in 3 weeks. "Elitot Confused" has been waiting two weeks for aaa so we do not have an estimated completion date for AAA. "Elitot Confused" has been waiting five weeks fo bbb and so we have stopped work on BBB. and so on. // Short version - Document everything!!!

        – MaxW
        Apr 5 at 17:55








      • 2





        Yes, "document everything" was the phrase I was looking for somewhere in these answers. That's the most important thing.

        – Dannie
        yesterday






      • 2





        @MaxW -- Your comment would make a good answer.

        – Jasper
        yesterday














      • 11





        Presumably there are formal contacts for the outsource company and the client company. Problems should be escalated to that level. The IT company should give regular feedback from that level. We completely X, and Y. Z will be completed in 3 weeks. "Elitot Confused" has been waiting two weeks for aaa so we do not have an estimated completion date for AAA. "Elitot Confused" has been waiting five weeks fo bbb and so we have stopped work on BBB. and so on. // Short version - Document everything!!!

        – MaxW
        Apr 5 at 17:55








      • 2





        Yes, "document everything" was the phrase I was looking for somewhere in these answers. That's the most important thing.

        – Dannie
        yesterday






      • 2





        @MaxW -- Your comment would make a good answer.

        – Jasper
        yesterday








      11




      11





      Presumably there are formal contacts for the outsource company and the client company. Problems should be escalated to that level. The IT company should give regular feedback from that level. We completely X, and Y. Z will be completed in 3 weeks. "Elitot Confused" has been waiting two weeks for aaa so we do not have an estimated completion date for AAA. "Elitot Confused" has been waiting five weeks fo bbb and so we have stopped work on BBB. and so on. // Short version - Document everything!!!

      – MaxW
      Apr 5 at 17:55







      Presumably there are formal contacts for the outsource company and the client company. Problems should be escalated to that level. The IT company should give regular feedback from that level. We completely X, and Y. Z will be completed in 3 weeks. "Elitot Confused" has been waiting two weeks for aaa so we do not have an estimated completion date for AAA. "Elitot Confused" has been waiting five weeks fo bbb and so we have stopped work on BBB. and so on. // Short version - Document everything!!!

      – MaxW
      Apr 5 at 17:55






      2




      2





      Yes, "document everything" was the phrase I was looking for somewhere in these answers. That's the most important thing.

      – Dannie
      yesterday





      Yes, "document everything" was the phrase I was looking for somewhere in these answers. That's the most important thing.

      – Dannie
      yesterday




      2




      2





      @MaxW -- Your comment would make a good answer.

      – Jasper
      yesterday





      @MaxW -- Your comment would make a good answer.

      – Jasper
      yesterday











      27














      Email the requests to the client team, and follow up with an email after the amount of time it would have taken you to comply with that request. CC this (nicely worded) reminder to the boss of the client company. They will either ignore it or help you out. If they ignore it, you have the paper trail to prove you are not the ones slowing the project, if they help you, all the better. After some iterations the boss of the client company will think of a way to reduce his spam-load, and give you a quick pass through (Some person just passing along the messages, as your own personal VPN).



      In parallel, try to establish a personal relationship with one or more members of the other team. The petty communication outages that they produce are a sign that they harbor personal resentment. This can often be remedied by face-to-face meet ups. I stress personal relationships. Not the 'let's implement X'-kind of conversation, but the 'public transport sure sucks, huh?'-common ground kind of conversation. Let them see the humans in your bunch of know-it-alls , and try yourself to see the humans in their bunch of nitwits.






      share|improve this answer


























      • Knowing the client, they will ignore the spam. We had a lot of chats and meeting with person of that team. Usually they stay on their ideas and we stay on ours. usually again ours proves to be correct and the client knows it (because we use solid proof to demonstrate our ideas)

        – Elitot Confused
        Apr 5 at 12:18






      • 3





        @ElitotConfused If they ignore the spam, you will have a BS job, but a paid BS job - find the mental place to deal with that, or quit; --- about the meetups: I stress personal relationships. Not the 'let's implement X'-kind of conversation, but the 'public transport sure sucks, huh?' kind of conversation. Let them see the humans in your bunch of know-it-alls , and try yourself to see the humans in their bunch of nitwits.

        – bukwyrm
        Apr 5 at 12:48
















      27














      Email the requests to the client team, and follow up with an email after the amount of time it would have taken you to comply with that request. CC this (nicely worded) reminder to the boss of the client company. They will either ignore it or help you out. If they ignore it, you have the paper trail to prove you are not the ones slowing the project, if they help you, all the better. After some iterations the boss of the client company will think of a way to reduce his spam-load, and give you a quick pass through (Some person just passing along the messages, as your own personal VPN).



      In parallel, try to establish a personal relationship with one or more members of the other team. The petty communication outages that they produce are a sign that they harbor personal resentment. This can often be remedied by face-to-face meet ups. I stress personal relationships. Not the 'let's implement X'-kind of conversation, but the 'public transport sure sucks, huh?'-common ground kind of conversation. Let them see the humans in your bunch of know-it-alls , and try yourself to see the humans in their bunch of nitwits.






      share|improve this answer


























      • Knowing the client, they will ignore the spam. We had a lot of chats and meeting with person of that team. Usually they stay on their ideas and we stay on ours. usually again ours proves to be correct and the client knows it (because we use solid proof to demonstrate our ideas)

        – Elitot Confused
        Apr 5 at 12:18






      • 3





        @ElitotConfused If they ignore the spam, you will have a BS job, but a paid BS job - find the mental place to deal with that, or quit; --- about the meetups: I stress personal relationships. Not the 'let's implement X'-kind of conversation, but the 'public transport sure sucks, huh?' kind of conversation. Let them see the humans in your bunch of know-it-alls , and try yourself to see the humans in their bunch of nitwits.

        – bukwyrm
        Apr 5 at 12:48














      27












      27








      27







      Email the requests to the client team, and follow up with an email after the amount of time it would have taken you to comply with that request. CC this (nicely worded) reminder to the boss of the client company. They will either ignore it or help you out. If they ignore it, you have the paper trail to prove you are not the ones slowing the project, if they help you, all the better. After some iterations the boss of the client company will think of a way to reduce his spam-load, and give you a quick pass through (Some person just passing along the messages, as your own personal VPN).



      In parallel, try to establish a personal relationship with one or more members of the other team. The petty communication outages that they produce are a sign that they harbor personal resentment. This can often be remedied by face-to-face meet ups. I stress personal relationships. Not the 'let's implement X'-kind of conversation, but the 'public transport sure sucks, huh?'-common ground kind of conversation. Let them see the humans in your bunch of know-it-alls , and try yourself to see the humans in their bunch of nitwits.






      share|improve this answer















      Email the requests to the client team, and follow up with an email after the amount of time it would have taken you to comply with that request. CC this (nicely worded) reminder to the boss of the client company. They will either ignore it or help you out. If they ignore it, you have the paper trail to prove you are not the ones slowing the project, if they help you, all the better. After some iterations the boss of the client company will think of a way to reduce his spam-load, and give you a quick pass through (Some person just passing along the messages, as your own personal VPN).



      In parallel, try to establish a personal relationship with one or more members of the other team. The petty communication outages that they produce are a sign that they harbor personal resentment. This can often be remedied by face-to-face meet ups. I stress personal relationships. Not the 'let's implement X'-kind of conversation, but the 'public transport sure sucks, huh?'-common ground kind of conversation. Let them see the humans in your bunch of know-it-alls , and try yourself to see the humans in their bunch of nitwits.







      share|improve this answer














      share|improve this answer



      share|improve this answer








      edited Apr 5 at 12:49

























      answered Apr 5 at 8:21









      bukwyrmbukwyrm

      71848




      71848













      • Knowing the client, they will ignore the spam. We had a lot of chats and meeting with person of that team. Usually they stay on their ideas and we stay on ours. usually again ours proves to be correct and the client knows it (because we use solid proof to demonstrate our ideas)

        – Elitot Confused
        Apr 5 at 12:18






      • 3





        @ElitotConfused If they ignore the spam, you will have a BS job, but a paid BS job - find the mental place to deal with that, or quit; --- about the meetups: I stress personal relationships. Not the 'let's implement X'-kind of conversation, but the 'public transport sure sucks, huh?' kind of conversation. Let them see the humans in your bunch of know-it-alls , and try yourself to see the humans in their bunch of nitwits.

        – bukwyrm
        Apr 5 at 12:48



















      • Knowing the client, they will ignore the spam. We had a lot of chats and meeting with person of that team. Usually they stay on their ideas and we stay on ours. usually again ours proves to be correct and the client knows it (because we use solid proof to demonstrate our ideas)

        – Elitot Confused
        Apr 5 at 12:18






      • 3





        @ElitotConfused If they ignore the spam, you will have a BS job, but a paid BS job - find the mental place to deal with that, or quit; --- about the meetups: I stress personal relationships. Not the 'let's implement X'-kind of conversation, but the 'public transport sure sucks, huh?' kind of conversation. Let them see the humans in your bunch of know-it-alls , and try yourself to see the humans in their bunch of nitwits.

        – bukwyrm
        Apr 5 at 12:48

















      Knowing the client, they will ignore the spam. We had a lot of chats and meeting with person of that team. Usually they stay on their ideas and we stay on ours. usually again ours proves to be correct and the client knows it (because we use solid proof to demonstrate our ideas)

      – Elitot Confused
      Apr 5 at 12:18





      Knowing the client, they will ignore the spam. We had a lot of chats and meeting with person of that team. Usually they stay on their ideas and we stay on ours. usually again ours proves to be correct and the client knows it (because we use solid proof to demonstrate our ideas)

      – Elitot Confused
      Apr 5 at 12:18




      3




      3





      @ElitotConfused If they ignore the spam, you will have a BS job, but a paid BS job - find the mental place to deal with that, or quit; --- about the meetups: I stress personal relationships. Not the 'let's implement X'-kind of conversation, but the 'public transport sure sucks, huh?' kind of conversation. Let them see the humans in your bunch of know-it-alls , and try yourself to see the humans in their bunch of nitwits.

      – bukwyrm
      Apr 5 at 12:48





      @ElitotConfused If they ignore the spam, you will have a BS job, but a paid BS job - find the mental place to deal with that, or quit; --- about the meetups: I stress personal relationships. Not the 'let's implement X'-kind of conversation, but the 'public transport sure sucks, huh?' kind of conversation. Let them see the humans in your bunch of know-it-alls , and try yourself to see the humans in their bunch of nitwits.

      – bukwyrm
      Apr 5 at 12:48











      12















      Client is well aware of the situation but he seems he wants to do
      nothing to solve.




      So, you've brought this to the attention of the "powers that be" and they're not interested in fixing the problem. I assume that they pay you for all of this "extra" work that you perform? If so, then either continue performing the work and continue getting paid for it or fire the client. There are no other options.






      share|improve this answer



















      • 1





        this is not helpful if for example boss of own company and boss of client insist on this relationship...

        – Allerleirauh
        Apr 5 at 7:41






      • 2





        @Allerleirauh "there are no other options" may not be helpful but it is the right answer

        – Pierre Arlaud
        Apr 5 at 12:02






      • 1





        We work on a body rental type of contract. There is no extra pay. the price is fixed at the beginning of the contract.

        – Elitot Confused
        Apr 5 at 12:23






      • 3





        @ElitotConfused I understand you saying that the cost per hour is fixed, but is the number of hours fixed or the product delivered (or both)? If it is both, you should find a new job. Otherwise, the cost has been increased--either they are paying for more hours (overtime) or they are paying for more hours (because it will take longer to get their product delivered).

        – user3067860
        Apr 5 at 18:33
















      12















      Client is well aware of the situation but he seems he wants to do
      nothing to solve.




      So, you've brought this to the attention of the "powers that be" and they're not interested in fixing the problem. I assume that they pay you for all of this "extra" work that you perform? If so, then either continue performing the work and continue getting paid for it or fire the client. There are no other options.






      share|improve this answer



















      • 1





        this is not helpful if for example boss of own company and boss of client insist on this relationship...

        – Allerleirauh
        Apr 5 at 7:41






      • 2





        @Allerleirauh "there are no other options" may not be helpful but it is the right answer

        – Pierre Arlaud
        Apr 5 at 12:02






      • 1





        We work on a body rental type of contract. There is no extra pay. the price is fixed at the beginning of the contract.

        – Elitot Confused
        Apr 5 at 12:23






      • 3





        @ElitotConfused I understand you saying that the cost per hour is fixed, but is the number of hours fixed or the product delivered (or both)? If it is both, you should find a new job. Otherwise, the cost has been increased--either they are paying for more hours (overtime) or they are paying for more hours (because it will take longer to get their product delivered).

        – user3067860
        Apr 5 at 18:33














      12












      12








      12








      Client is well aware of the situation but he seems he wants to do
      nothing to solve.




      So, you've brought this to the attention of the "powers that be" and they're not interested in fixing the problem. I assume that they pay you for all of this "extra" work that you perform? If so, then either continue performing the work and continue getting paid for it or fire the client. There are no other options.






      share|improve this answer














      Client is well aware of the situation but he seems he wants to do
      nothing to solve.




      So, you've brought this to the attention of the "powers that be" and they're not interested in fixing the problem. I assume that they pay you for all of this "extra" work that you perform? If so, then either continue performing the work and continue getting paid for it or fire the client. There are no other options.







      share|improve this answer












      share|improve this answer



      share|improve this answer










      answered Apr 5 at 7:39









      joeqwertyjoeqwerty

      2,403517




      2,403517








      • 1





        this is not helpful if for example boss of own company and boss of client insist on this relationship...

        – Allerleirauh
        Apr 5 at 7:41






      • 2





        @Allerleirauh "there are no other options" may not be helpful but it is the right answer

        – Pierre Arlaud
        Apr 5 at 12:02






      • 1





        We work on a body rental type of contract. There is no extra pay. the price is fixed at the beginning of the contract.

        – Elitot Confused
        Apr 5 at 12:23






      • 3





        @ElitotConfused I understand you saying that the cost per hour is fixed, but is the number of hours fixed or the product delivered (or both)? If it is both, you should find a new job. Otherwise, the cost has been increased--either they are paying for more hours (overtime) or they are paying for more hours (because it will take longer to get their product delivered).

        – user3067860
        Apr 5 at 18:33














      • 1





        this is not helpful if for example boss of own company and boss of client insist on this relationship...

        – Allerleirauh
        Apr 5 at 7:41






      • 2





        @Allerleirauh "there are no other options" may not be helpful but it is the right answer

        – Pierre Arlaud
        Apr 5 at 12:02






      • 1





        We work on a body rental type of contract. There is no extra pay. the price is fixed at the beginning of the contract.

        – Elitot Confused
        Apr 5 at 12:23






      • 3





        @ElitotConfused I understand you saying that the cost per hour is fixed, but is the number of hours fixed or the product delivered (or both)? If it is both, you should find a new job. Otherwise, the cost has been increased--either they are paying for more hours (overtime) or they are paying for more hours (because it will take longer to get their product delivered).

        – user3067860
        Apr 5 at 18:33








      1




      1





      this is not helpful if for example boss of own company and boss of client insist on this relationship...

      – Allerleirauh
      Apr 5 at 7:41





      this is not helpful if for example boss of own company and boss of client insist on this relationship...

      – Allerleirauh
      Apr 5 at 7:41




      2




      2





      @Allerleirauh "there are no other options" may not be helpful but it is the right answer

      – Pierre Arlaud
      Apr 5 at 12:02





      @Allerleirauh "there are no other options" may not be helpful but it is the right answer

      – Pierre Arlaud
      Apr 5 at 12:02




      1




      1





      We work on a body rental type of contract. There is no extra pay. the price is fixed at the beginning of the contract.

      – Elitot Confused
      Apr 5 at 12:23





      We work on a body rental type of contract. There is no extra pay. the price is fixed at the beginning of the contract.

      – Elitot Confused
      Apr 5 at 12:23




      3




      3





      @ElitotConfused I understand you saying that the cost per hour is fixed, but is the number of hours fixed or the product delivered (or both)? If it is both, you should find a new job. Otherwise, the cost has been increased--either they are paying for more hours (overtime) or they are paying for more hours (because it will take longer to get their product delivered).

      – user3067860
      Apr 5 at 18:33





      @ElitotConfused I understand you saying that the cost per hour is fixed, but is the number of hours fixed or the product delivered (or both)? If it is both, you should find a new job. Otherwise, the cost has been increased--either they are paying for more hours (overtime) or they are paying for more hours (because it will take longer to get their product delivered).

      – user3067860
      Apr 5 at 18:33











      6














      Ask for a regular status meeting with the client (hopefully you have that already but I get the sense that you don't). (NOTE: By regular I mean at least weekly, if not 2-3 times a week. If you can swing it, a stand up every day would be ideal.) During this status meeting, talk about the roadblocks you currently have... list them one by one, what you need, what you are waiting for and from whom, and what the dangers are if the request isn't filled in a timely manner... the project quality will suffer, you will ship late, etc.




      We sent an email last week that we need X from the suppliers and that we would need it within a week in order to not put the project deadline in danger. We are rapidly approaching a week since our request. Do you have any updates on when we might get X? If we don't get it by this Friday, we will have to push back the delivery date by a week.



      We sent an email last week to Jim asking for clarification on the Widget code. We can't proceed until we get that clarification. When can we set up that meeting?




      and so on. Don't be accusatory or emotional, be factual, be clear about what problems this issue is causing or will cause to the project. When you don't get X for 3 weeks and you needed it the next day, no one should be surprised when you state that the delivery date will slip by 3 weeks.



      Once things start looking like you won't ship on the initially agreed upon time, start communicating regularly with the client management. Inform them that the X, Y, and Z delays that you have notified them of are of their teams' doing and will put you past the scheduled timeframe. Any additional work past X date will incur additional at the rate of $Z. (Maybe it's too late to do some of this but you can at least start dropping hints of contract renegotiation due to delays beyond your control and of the client company's making).






      share|improve this answer



















      • 2





        Yup. Status meeting should have the Joe Friday approach. "Just the facts sir..." It is not a place to brainstorm solutions. So the client contact takes a todo to have Joe at client's site respond or to find out when Joe will respond.

        – MaxW
        Apr 5 at 18:03
















      6














      Ask for a regular status meeting with the client (hopefully you have that already but I get the sense that you don't). (NOTE: By regular I mean at least weekly, if not 2-3 times a week. If you can swing it, a stand up every day would be ideal.) During this status meeting, talk about the roadblocks you currently have... list them one by one, what you need, what you are waiting for and from whom, and what the dangers are if the request isn't filled in a timely manner... the project quality will suffer, you will ship late, etc.




      We sent an email last week that we need X from the suppliers and that we would need it within a week in order to not put the project deadline in danger. We are rapidly approaching a week since our request. Do you have any updates on when we might get X? If we don't get it by this Friday, we will have to push back the delivery date by a week.



      We sent an email last week to Jim asking for clarification on the Widget code. We can't proceed until we get that clarification. When can we set up that meeting?




      and so on. Don't be accusatory or emotional, be factual, be clear about what problems this issue is causing or will cause to the project. When you don't get X for 3 weeks and you needed it the next day, no one should be surprised when you state that the delivery date will slip by 3 weeks.



      Once things start looking like you won't ship on the initially agreed upon time, start communicating regularly with the client management. Inform them that the X, Y, and Z delays that you have notified them of are of their teams' doing and will put you past the scheduled timeframe. Any additional work past X date will incur additional at the rate of $Z. (Maybe it's too late to do some of this but you can at least start dropping hints of contract renegotiation due to delays beyond your control and of the client company's making).






      share|improve this answer



















      • 2





        Yup. Status meeting should have the Joe Friday approach. "Just the facts sir..." It is not a place to brainstorm solutions. So the client contact takes a todo to have Joe at client's site respond or to find out when Joe will respond.

        – MaxW
        Apr 5 at 18:03














      6












      6








      6







      Ask for a regular status meeting with the client (hopefully you have that already but I get the sense that you don't). (NOTE: By regular I mean at least weekly, if not 2-3 times a week. If you can swing it, a stand up every day would be ideal.) During this status meeting, talk about the roadblocks you currently have... list them one by one, what you need, what you are waiting for and from whom, and what the dangers are if the request isn't filled in a timely manner... the project quality will suffer, you will ship late, etc.




      We sent an email last week that we need X from the suppliers and that we would need it within a week in order to not put the project deadline in danger. We are rapidly approaching a week since our request. Do you have any updates on when we might get X? If we don't get it by this Friday, we will have to push back the delivery date by a week.



      We sent an email last week to Jim asking for clarification on the Widget code. We can't proceed until we get that clarification. When can we set up that meeting?




      and so on. Don't be accusatory or emotional, be factual, be clear about what problems this issue is causing or will cause to the project. When you don't get X for 3 weeks and you needed it the next day, no one should be surprised when you state that the delivery date will slip by 3 weeks.



      Once things start looking like you won't ship on the initially agreed upon time, start communicating regularly with the client management. Inform them that the X, Y, and Z delays that you have notified them of are of their teams' doing and will put you past the scheduled timeframe. Any additional work past X date will incur additional at the rate of $Z. (Maybe it's too late to do some of this but you can at least start dropping hints of contract renegotiation due to delays beyond your control and of the client company's making).






      share|improve this answer













      Ask for a regular status meeting with the client (hopefully you have that already but I get the sense that you don't). (NOTE: By regular I mean at least weekly, if not 2-3 times a week. If you can swing it, a stand up every day would be ideal.) During this status meeting, talk about the roadblocks you currently have... list them one by one, what you need, what you are waiting for and from whom, and what the dangers are if the request isn't filled in a timely manner... the project quality will suffer, you will ship late, etc.




      We sent an email last week that we need X from the suppliers and that we would need it within a week in order to not put the project deadline in danger. We are rapidly approaching a week since our request. Do you have any updates on when we might get X? If we don't get it by this Friday, we will have to push back the delivery date by a week.



      We sent an email last week to Jim asking for clarification on the Widget code. We can't proceed until we get that clarification. When can we set up that meeting?




      and so on. Don't be accusatory or emotional, be factual, be clear about what problems this issue is causing or will cause to the project. When you don't get X for 3 weeks and you needed it the next day, no one should be surprised when you state that the delivery date will slip by 3 weeks.



      Once things start looking like you won't ship on the initially agreed upon time, start communicating regularly with the client management. Inform them that the X, Y, and Z delays that you have notified them of are of their teams' doing and will put you past the scheduled timeframe. Any additional work past X date will incur additional at the rate of $Z. (Maybe it's too late to do some of this but you can at least start dropping hints of contract renegotiation due to delays beyond your control and of the client company's making).







      share|improve this answer












      share|improve this answer



      share|improve this answer










      answered Apr 5 at 15:15









      JeffCJeffC

      1,6651613




      1,6651613








      • 2





        Yup. Status meeting should have the Joe Friday approach. "Just the facts sir..." It is not a place to brainstorm solutions. So the client contact takes a todo to have Joe at client's site respond or to find out when Joe will respond.

        – MaxW
        Apr 5 at 18:03














      • 2





        Yup. Status meeting should have the Joe Friday approach. "Just the facts sir..." It is not a place to brainstorm solutions. So the client contact takes a todo to have Joe at client's site respond or to find out when Joe will respond.

        – MaxW
        Apr 5 at 18:03








      2




      2





      Yup. Status meeting should have the Joe Friday approach. "Just the facts sir..." It is not a place to brainstorm solutions. So the client contact takes a todo to have Joe at client's site respond or to find out when Joe will respond.

      – MaxW
      Apr 5 at 18:03





      Yup. Status meeting should have the Joe Friday approach. "Just the facts sir..." It is not a place to brainstorm solutions. So the client contact takes a todo to have Joe at client's site respond or to find out when Joe will respond.

      – MaxW
      Apr 5 at 18:03











      3














      Here is what I read:




      • We are great

      • Client not so much

      • They don't like us


      Pro-tip, sometimes it better to be liked than right. Who do you want to be friends with more, the boss man, or the workers? Boss man pays the bills so always be his friend. But sometimes it helps to be friends with the workers also.



      So instead of "Us" versus "Them", try to make it "We".



      Rule #1: BE NICE



      I'm sure you are always very professional, but from what you said in your post, I'm doubting you are always nice.



      Sometimes a friendly visit to the client, box of donuts/candy/meat-veg tray/ice cream/movie tickets/etc... can go along way. Basically say, "we want to get along, we want to help you, we are on your side."



      This isn't so much a reward, since it doesn't sound like you are in a position to reward or punish. Its more about trying to change the perception of the other team about you from "they are our enemies" to "they are our friends".



      Rule #2: Be in control



      If I was manager in this situation, I would say, "how can we manage the code better".



      If possible, I'd maintain a separate Git repo, where you can add their contributions as separate pull requests. If they are stuck on SVN, so be it. You can give them your contributions as big single commits. Even if you have to move the code manually, its better than the client team screwing up the repo your team depends on.



      Don't let their bad commits and bad SVN practices control your productivity.



      Also, like the other posts said, document communications in case you need to CYA.



      Good luck!






      share|improve this answer










      New contributor




      Turtle1363 is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
      Check out our Code of Conduct.
















      • 3





        Seriously? You're suggesting to reward obstructionist and unprofessional behaviour by buying another company's employees .. ice cream and movie tickets?

        – Lightness Races in Orbit
        2 days ago













      • And SVN is not the problem here.

        – Lightness Races in Orbit
        2 days ago











      • @LightnessRacesinOrbit sometimes the carrot works better than the stick. It’s not about “rewarding” so much as strategies for controlling the situation to obtain the desired outcome.

        – Turtle1363
        2 days ago








      • 4





        If I were wilfully ignoring a team for weeks on end, then they turned up to give me movie tickets, I'd find that really awkward and weird.

        – Lightness Races in Orbit
        2 days ago






      • 2





        @LightnessRacesinOrbit, maybe? Relationships can be awkward and weird. That's when you pull the team lead aside and say something to the effect of, "I feel like our communication hasn't been the best lately. I want you to know that we are here for you, and we all have the same goal of wanting the company to succeed. I just wanted to give you this small token, I hope you enjoy it. If you need anything please let us know. We are looking forward to the new challenges and opportunities in the next few weeks, I hope I can count on you for your support."

        – Turtle1363
        2 days ago
















      3














      Here is what I read:




      • We are great

      • Client not so much

      • They don't like us


      Pro-tip, sometimes it better to be liked than right. Who do you want to be friends with more, the boss man, or the workers? Boss man pays the bills so always be his friend. But sometimes it helps to be friends with the workers also.



      So instead of "Us" versus "Them", try to make it "We".



      Rule #1: BE NICE



      I'm sure you are always very professional, but from what you said in your post, I'm doubting you are always nice.



      Sometimes a friendly visit to the client, box of donuts/candy/meat-veg tray/ice cream/movie tickets/etc... can go along way. Basically say, "we want to get along, we want to help you, we are on your side."



      This isn't so much a reward, since it doesn't sound like you are in a position to reward or punish. Its more about trying to change the perception of the other team about you from "they are our enemies" to "they are our friends".



      Rule #2: Be in control



      If I was manager in this situation, I would say, "how can we manage the code better".



      If possible, I'd maintain a separate Git repo, where you can add their contributions as separate pull requests. If they are stuck on SVN, so be it. You can give them your contributions as big single commits. Even if you have to move the code manually, its better than the client team screwing up the repo your team depends on.



      Don't let their bad commits and bad SVN practices control your productivity.



      Also, like the other posts said, document communications in case you need to CYA.



      Good luck!






      share|improve this answer










      New contributor




      Turtle1363 is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
      Check out our Code of Conduct.
















      • 3





        Seriously? You're suggesting to reward obstructionist and unprofessional behaviour by buying another company's employees .. ice cream and movie tickets?

        – Lightness Races in Orbit
        2 days ago













      • And SVN is not the problem here.

        – Lightness Races in Orbit
        2 days ago











      • @LightnessRacesinOrbit sometimes the carrot works better than the stick. It’s not about “rewarding” so much as strategies for controlling the situation to obtain the desired outcome.

        – Turtle1363
        2 days ago








      • 4





        If I were wilfully ignoring a team for weeks on end, then they turned up to give me movie tickets, I'd find that really awkward and weird.

        – Lightness Races in Orbit
        2 days ago






      • 2





        @LightnessRacesinOrbit, maybe? Relationships can be awkward and weird. That's when you pull the team lead aside and say something to the effect of, "I feel like our communication hasn't been the best lately. I want you to know that we are here for you, and we all have the same goal of wanting the company to succeed. I just wanted to give you this small token, I hope you enjoy it. If you need anything please let us know. We are looking forward to the new challenges and opportunities in the next few weeks, I hope I can count on you for your support."

        – Turtle1363
        2 days ago














      3












      3








      3







      Here is what I read:




      • We are great

      • Client not so much

      • They don't like us


      Pro-tip, sometimes it better to be liked than right. Who do you want to be friends with more, the boss man, or the workers? Boss man pays the bills so always be his friend. But sometimes it helps to be friends with the workers also.



      So instead of "Us" versus "Them", try to make it "We".



      Rule #1: BE NICE



      I'm sure you are always very professional, but from what you said in your post, I'm doubting you are always nice.



      Sometimes a friendly visit to the client, box of donuts/candy/meat-veg tray/ice cream/movie tickets/etc... can go along way. Basically say, "we want to get along, we want to help you, we are on your side."



      This isn't so much a reward, since it doesn't sound like you are in a position to reward or punish. Its more about trying to change the perception of the other team about you from "they are our enemies" to "they are our friends".



      Rule #2: Be in control



      If I was manager in this situation, I would say, "how can we manage the code better".



      If possible, I'd maintain a separate Git repo, where you can add their contributions as separate pull requests. If they are stuck on SVN, so be it. You can give them your contributions as big single commits. Even if you have to move the code manually, its better than the client team screwing up the repo your team depends on.



      Don't let their bad commits and bad SVN practices control your productivity.



      Also, like the other posts said, document communications in case you need to CYA.



      Good luck!






      share|improve this answer










      New contributor




      Turtle1363 is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
      Check out our Code of Conduct.










      Here is what I read:




      • We are great

      • Client not so much

      • They don't like us


      Pro-tip, sometimes it better to be liked than right. Who do you want to be friends with more, the boss man, or the workers? Boss man pays the bills so always be his friend. But sometimes it helps to be friends with the workers also.



      So instead of "Us" versus "Them", try to make it "We".



      Rule #1: BE NICE



      I'm sure you are always very professional, but from what you said in your post, I'm doubting you are always nice.



      Sometimes a friendly visit to the client, box of donuts/candy/meat-veg tray/ice cream/movie tickets/etc... can go along way. Basically say, "we want to get along, we want to help you, we are on your side."



      This isn't so much a reward, since it doesn't sound like you are in a position to reward or punish. Its more about trying to change the perception of the other team about you from "they are our enemies" to "they are our friends".



      Rule #2: Be in control



      If I was manager in this situation, I would say, "how can we manage the code better".



      If possible, I'd maintain a separate Git repo, where you can add their contributions as separate pull requests. If they are stuck on SVN, so be it. You can give them your contributions as big single commits. Even if you have to move the code manually, its better than the client team screwing up the repo your team depends on.



      Don't let their bad commits and bad SVN practices control your productivity.



      Also, like the other posts said, document communications in case you need to CYA.



      Good luck!







      share|improve this answer










      New contributor




      Turtle1363 is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
      Check out our Code of Conduct.









      share|improve this answer



      share|improve this answer








      edited 2 days ago





















      New contributor




      Turtle1363 is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
      Check out our Code of Conduct.









      answered Apr 5 at 21:39









      Turtle1363Turtle1363

      1394




      1394




      New contributor




      Turtle1363 is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
      Check out our Code of Conduct.





      New contributor





      Turtle1363 is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
      Check out our Code of Conduct.






      Turtle1363 is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
      Check out our Code of Conduct.








      • 3





        Seriously? You're suggesting to reward obstructionist and unprofessional behaviour by buying another company's employees .. ice cream and movie tickets?

        – Lightness Races in Orbit
        2 days ago













      • And SVN is not the problem here.

        – Lightness Races in Orbit
        2 days ago











      • @LightnessRacesinOrbit sometimes the carrot works better than the stick. It’s not about “rewarding” so much as strategies for controlling the situation to obtain the desired outcome.

        – Turtle1363
        2 days ago








      • 4





        If I were wilfully ignoring a team for weeks on end, then they turned up to give me movie tickets, I'd find that really awkward and weird.

        – Lightness Races in Orbit
        2 days ago






      • 2





        @LightnessRacesinOrbit, maybe? Relationships can be awkward and weird. That's when you pull the team lead aside and say something to the effect of, "I feel like our communication hasn't been the best lately. I want you to know that we are here for you, and we all have the same goal of wanting the company to succeed. I just wanted to give you this small token, I hope you enjoy it. If you need anything please let us know. We are looking forward to the new challenges and opportunities in the next few weeks, I hope I can count on you for your support."

        – Turtle1363
        2 days ago














      • 3





        Seriously? You're suggesting to reward obstructionist and unprofessional behaviour by buying another company's employees .. ice cream and movie tickets?

        – Lightness Races in Orbit
        2 days ago













      • And SVN is not the problem here.

        – Lightness Races in Orbit
        2 days ago











      • @LightnessRacesinOrbit sometimes the carrot works better than the stick. It’s not about “rewarding” so much as strategies for controlling the situation to obtain the desired outcome.

        – Turtle1363
        2 days ago








      • 4





        If I were wilfully ignoring a team for weeks on end, then they turned up to give me movie tickets, I'd find that really awkward and weird.

        – Lightness Races in Orbit
        2 days ago






      • 2





        @LightnessRacesinOrbit, maybe? Relationships can be awkward and weird. That's when you pull the team lead aside and say something to the effect of, "I feel like our communication hasn't been the best lately. I want you to know that we are here for you, and we all have the same goal of wanting the company to succeed. I just wanted to give you this small token, I hope you enjoy it. If you need anything please let us know. We are looking forward to the new challenges and opportunities in the next few weeks, I hope I can count on you for your support."

        – Turtle1363
        2 days ago








      3




      3





      Seriously? You're suggesting to reward obstructionist and unprofessional behaviour by buying another company's employees .. ice cream and movie tickets?

      – Lightness Races in Orbit
      2 days ago







      Seriously? You're suggesting to reward obstructionist and unprofessional behaviour by buying another company's employees .. ice cream and movie tickets?

      – Lightness Races in Orbit
      2 days ago















      And SVN is not the problem here.

      – Lightness Races in Orbit
      2 days ago





      And SVN is not the problem here.

      – Lightness Races in Orbit
      2 days ago













      @LightnessRacesinOrbit sometimes the carrot works better than the stick. It’s not about “rewarding” so much as strategies for controlling the situation to obtain the desired outcome.

      – Turtle1363
      2 days ago







      @LightnessRacesinOrbit sometimes the carrot works better than the stick. It’s not about “rewarding” so much as strategies for controlling the situation to obtain the desired outcome.

      – Turtle1363
      2 days ago






      4




      4





      If I were wilfully ignoring a team for weeks on end, then they turned up to give me movie tickets, I'd find that really awkward and weird.

      – Lightness Races in Orbit
      2 days ago





      If I were wilfully ignoring a team for weeks on end, then they turned up to give me movie tickets, I'd find that really awkward and weird.

      – Lightness Races in Orbit
      2 days ago




      2




      2





      @LightnessRacesinOrbit, maybe? Relationships can be awkward and weird. That's when you pull the team lead aside and say something to the effect of, "I feel like our communication hasn't been the best lately. I want you to know that we are here for you, and we all have the same goal of wanting the company to succeed. I just wanted to give you this small token, I hope you enjoy it. If you need anything please let us know. We are looking forward to the new challenges and opportunities in the next few weeks, I hope I can count on you for your support."

      – Turtle1363
      2 days ago





      @LightnessRacesinOrbit, maybe? Relationships can be awkward and weird. That's when you pull the team lead aside and say something to the effect of, "I feel like our communication hasn't been the best lately. I want you to know that we are here for you, and we all have the same goal of wanting the company to succeed. I just wanted to give you this small token, I hope you enjoy it. If you need anything please let us know. We are looking forward to the new challenges and opportunities in the next few weeks, I hope I can count on you for your support."

      – Turtle1363
      2 days ago











      2














      Document each request, each complaint, and the hours wasted trying to work through the internal team to get the resources you need.



      Right now, the internal team is fighting you because, so far, you have proven more capable of handling the application and are upstaging them - they are retaliating by making things more difficult for you.



      Continue to provide the support you have thus far, and keep your client in the loop about all of these hang-ups. CC them, if you can, so that they are well aware of your attempts to keep things moving.



      Eventually, they will have to confront this issue - but this is not your problem to solve. Your only concern should be getting your own work done, and showing that you are doing everything you can to get the resources for that work.



      So long as you are doing your work to the degree you've described thus far, with the only complications being the internal team, they should have no reason to break off ties with you (though, they may want to consider restructuring that team - but again, this is not your problem to solve).






      share|improve this answer
























      • +1 this seems the right answer. An excel sheet with emails and how long they are delayed, can go a long way.

        – Rui F Ribeiro
        2 days ago
















      2














      Document each request, each complaint, and the hours wasted trying to work through the internal team to get the resources you need.



      Right now, the internal team is fighting you because, so far, you have proven more capable of handling the application and are upstaging them - they are retaliating by making things more difficult for you.



      Continue to provide the support you have thus far, and keep your client in the loop about all of these hang-ups. CC them, if you can, so that they are well aware of your attempts to keep things moving.



      Eventually, they will have to confront this issue - but this is not your problem to solve. Your only concern should be getting your own work done, and showing that you are doing everything you can to get the resources for that work.



      So long as you are doing your work to the degree you've described thus far, with the only complications being the internal team, they should have no reason to break off ties with you (though, they may want to consider restructuring that team - but again, this is not your problem to solve).






      share|improve this answer
























      • +1 this seems the right answer. An excel sheet with emails and how long they are delayed, can go a long way.

        – Rui F Ribeiro
        2 days ago














      2












      2








      2







      Document each request, each complaint, and the hours wasted trying to work through the internal team to get the resources you need.



      Right now, the internal team is fighting you because, so far, you have proven more capable of handling the application and are upstaging them - they are retaliating by making things more difficult for you.



      Continue to provide the support you have thus far, and keep your client in the loop about all of these hang-ups. CC them, if you can, so that they are well aware of your attempts to keep things moving.



      Eventually, they will have to confront this issue - but this is not your problem to solve. Your only concern should be getting your own work done, and showing that you are doing everything you can to get the resources for that work.



      So long as you are doing your work to the degree you've described thus far, with the only complications being the internal team, they should have no reason to break off ties with you (though, they may want to consider restructuring that team - but again, this is not your problem to solve).






      share|improve this answer













      Document each request, each complaint, and the hours wasted trying to work through the internal team to get the resources you need.



      Right now, the internal team is fighting you because, so far, you have proven more capable of handling the application and are upstaging them - they are retaliating by making things more difficult for you.



      Continue to provide the support you have thus far, and keep your client in the loop about all of these hang-ups. CC them, if you can, so that they are well aware of your attempts to keep things moving.



      Eventually, they will have to confront this issue - but this is not your problem to solve. Your only concern should be getting your own work done, and showing that you are doing everything you can to get the resources for that work.



      So long as you are doing your work to the degree you've described thus far, with the only complications being the internal team, they should have no reason to break off ties with you (though, they may want to consider restructuring that team - but again, this is not your problem to solve).







      share|improve this answer












      share|improve this answer



      share|improve this answer










      answered Apr 5 at 15:49









      ZibbobzZibbobz

      7,14952656




      7,14952656













      • +1 this seems the right answer. An excel sheet with emails and how long they are delayed, can go a long way.

        – Rui F Ribeiro
        2 days ago



















      • +1 this seems the right answer. An excel sheet with emails and how long they are delayed, can go a long way.

        – Rui F Ribeiro
        2 days ago

















      +1 this seems the right answer. An excel sheet with emails and how long they are delayed, can go a long way.

      – Rui F Ribeiro
      2 days ago





      +1 this seems the right answer. An excel sheet with emails and how long they are delayed, can go a long way.

      – Rui F Ribeiro
      2 days ago











      1














      Where is the client internal team located? Is there a possibility that somebody from your team can go to the site where the internal team is located? I have had experiences in the past with teams that were difficult to work with, and I find that the best solution is to just go down and talk with people directly. I have had to spend entire days tracking down information myself from internal teams, just because the communication and initiative was simply not there. There is no need to be abrasive, or confrontational, just show up and get the communication lines established. Find out if they have a weekly meeting and have someone attend it. The bottom line is that the other team is struggling and your work is showing that to everyone. They are defensive for a good reason, so just show up with the attitude of "how can we help each other?". Maybe you can start doing some mentoring, or help them improve their process. You are hired as consultants not just to deliver the project, but to enhance the company/team.






      share|improve this answer








      New contributor




      Brian Y is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
      Check out our Code of Conduct.

























        1














        Where is the client internal team located? Is there a possibility that somebody from your team can go to the site where the internal team is located? I have had experiences in the past with teams that were difficult to work with, and I find that the best solution is to just go down and talk with people directly. I have had to spend entire days tracking down information myself from internal teams, just because the communication and initiative was simply not there. There is no need to be abrasive, or confrontational, just show up and get the communication lines established. Find out if they have a weekly meeting and have someone attend it. The bottom line is that the other team is struggling and your work is showing that to everyone. They are defensive for a good reason, so just show up with the attitude of "how can we help each other?". Maybe you can start doing some mentoring, or help them improve their process. You are hired as consultants not just to deliver the project, but to enhance the company/team.






        share|improve this answer








        New contributor




        Brian Y is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
        Check out our Code of Conduct.























          1












          1








          1







          Where is the client internal team located? Is there a possibility that somebody from your team can go to the site where the internal team is located? I have had experiences in the past with teams that were difficult to work with, and I find that the best solution is to just go down and talk with people directly. I have had to spend entire days tracking down information myself from internal teams, just because the communication and initiative was simply not there. There is no need to be abrasive, or confrontational, just show up and get the communication lines established. Find out if they have a weekly meeting and have someone attend it. The bottom line is that the other team is struggling and your work is showing that to everyone. They are defensive for a good reason, so just show up with the attitude of "how can we help each other?". Maybe you can start doing some mentoring, or help them improve their process. You are hired as consultants not just to deliver the project, but to enhance the company/team.






          share|improve this answer








          New contributor




          Brian Y is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
          Check out our Code of Conduct.










          Where is the client internal team located? Is there a possibility that somebody from your team can go to the site where the internal team is located? I have had experiences in the past with teams that were difficult to work with, and I find that the best solution is to just go down and talk with people directly. I have had to spend entire days tracking down information myself from internal teams, just because the communication and initiative was simply not there. There is no need to be abrasive, or confrontational, just show up and get the communication lines established. Find out if they have a weekly meeting and have someone attend it. The bottom line is that the other team is struggling and your work is showing that to everyone. They are defensive for a good reason, so just show up with the attitude of "how can we help each other?". Maybe you can start doing some mentoring, or help them improve their process. You are hired as consultants not just to deliver the project, but to enhance the company/team.







          share|improve this answer








          New contributor




          Brian Y is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
          Check out our Code of Conduct.









          share|improve this answer



          share|improve this answer






          New contributor




          Brian Y is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
          Check out our Code of Conduct.









          answered Apr 5 at 22:26









          Brian YBrian Y

          1112




          1112




          New contributor




          Brian Y is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
          Check out our Code of Conduct.





          New contributor





          Brian Y is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
          Check out our Code of Conduct.






          Brian Y is a new contributor to this site. Take care in asking for clarification, commenting, and answering.
          Check out our Code of Conduct.























              0














              So I've read the existing answers and there's more to deal with.




              Send your invoice to your client for your time.




              Correct; however we also now have an employee morale problem on your side; or if we don't we will soon. Whatever cheapish things you can do to keep morale up, it's time to start doing them.



              You may have to approach your customer with something along the lines of "Due to certain problems on your side causing an employee morale problem for us, we have to increase our future rates for you by about 10% so that we can buy perks for the employees." But please, find somebody more diplomatic than I.






              share|improve this answer



















              • 2





                OP is not the boss, so I don't think this answer makes sense for them.

                – user87779
                Apr 5 at 20:03











              • @user87779: In which case the morale problem will have to propagate upwards until it does reach someone who can act on it.

                – Joshua
                Apr 5 at 21:52











              • exactly, i agree. So maybe edit the answer to say that, and maybe a way for the OP to help if happen if you think they can.

                – user87779
                Apr 5 at 21:55













              • @user87779: I don't suppose you could splice an edit in? I've ran out of ability (which is why my rep stays low...)

                – Joshua
                Apr 5 at 23:04











              • huh, I'm not able to either. I wonder if the question was protected or something weird.

                – user87779
                Apr 6 at 0:34
















              0














              So I've read the existing answers and there's more to deal with.




              Send your invoice to your client for your time.




              Correct; however we also now have an employee morale problem on your side; or if we don't we will soon. Whatever cheapish things you can do to keep morale up, it's time to start doing them.



              You may have to approach your customer with something along the lines of "Due to certain problems on your side causing an employee morale problem for us, we have to increase our future rates for you by about 10% so that we can buy perks for the employees." But please, find somebody more diplomatic than I.






              share|improve this answer



















              • 2





                OP is not the boss, so I don't think this answer makes sense for them.

                – user87779
                Apr 5 at 20:03











              • @user87779: In which case the morale problem will have to propagate upwards until it does reach someone who can act on it.

                – Joshua
                Apr 5 at 21:52











              • exactly, i agree. So maybe edit the answer to say that, and maybe a way for the OP to help if happen if you think they can.

                – user87779
                Apr 5 at 21:55













              • @user87779: I don't suppose you could splice an edit in? I've ran out of ability (which is why my rep stays low...)

                – Joshua
                Apr 5 at 23:04











              • huh, I'm not able to either. I wonder if the question was protected or something weird.

                – user87779
                Apr 6 at 0:34














              0












              0








              0







              So I've read the existing answers and there's more to deal with.




              Send your invoice to your client for your time.




              Correct; however we also now have an employee morale problem on your side; or if we don't we will soon. Whatever cheapish things you can do to keep morale up, it's time to start doing them.



              You may have to approach your customer with something along the lines of "Due to certain problems on your side causing an employee morale problem for us, we have to increase our future rates for you by about 10% so that we can buy perks for the employees." But please, find somebody more diplomatic than I.






              share|improve this answer













              So I've read the existing answers and there's more to deal with.




              Send your invoice to your client for your time.




              Correct; however we also now have an employee morale problem on your side; or if we don't we will soon. Whatever cheapish things you can do to keep morale up, it's time to start doing them.



              You may have to approach your customer with something along the lines of "Due to certain problems on your side causing an employee morale problem for us, we have to increase our future rates for you by about 10% so that we can buy perks for the employees." But please, find somebody more diplomatic than I.







              share|improve this answer












              share|improve this answer



              share|improve this answer










              answered Apr 5 at 15:56









              JoshuaJoshua

              525412




              525412








              • 2





                OP is not the boss, so I don't think this answer makes sense for them.

                – user87779
                Apr 5 at 20:03











              • @user87779: In which case the morale problem will have to propagate upwards until it does reach someone who can act on it.

                – Joshua
                Apr 5 at 21:52











              • exactly, i agree. So maybe edit the answer to say that, and maybe a way for the OP to help if happen if you think they can.

                – user87779
                Apr 5 at 21:55













              • @user87779: I don't suppose you could splice an edit in? I've ran out of ability (which is why my rep stays low...)

                – Joshua
                Apr 5 at 23:04











              • huh, I'm not able to either. I wonder if the question was protected or something weird.

                – user87779
                Apr 6 at 0:34














              • 2





                OP is not the boss, so I don't think this answer makes sense for them.

                – user87779
                Apr 5 at 20:03











              • @user87779: In which case the morale problem will have to propagate upwards until it does reach someone who can act on it.

                – Joshua
                Apr 5 at 21:52











              • exactly, i agree. So maybe edit the answer to say that, and maybe a way for the OP to help if happen if you think they can.

                – user87779
                Apr 5 at 21:55













              • @user87779: I don't suppose you could splice an edit in? I've ran out of ability (which is why my rep stays low...)

                – Joshua
                Apr 5 at 23:04











              • huh, I'm not able to either. I wonder if the question was protected or something weird.

                – user87779
                Apr 6 at 0:34








              2




              2





              OP is not the boss, so I don't think this answer makes sense for them.

              – user87779
              Apr 5 at 20:03





              OP is not the boss, so I don't think this answer makes sense for them.

              – user87779
              Apr 5 at 20:03













              @user87779: In which case the morale problem will have to propagate upwards until it does reach someone who can act on it.

              – Joshua
              Apr 5 at 21:52





              @user87779: In which case the morale problem will have to propagate upwards until it does reach someone who can act on it.

              – Joshua
              Apr 5 at 21:52













              exactly, i agree. So maybe edit the answer to say that, and maybe a way for the OP to help if happen if you think they can.

              – user87779
              Apr 5 at 21:55







              exactly, i agree. So maybe edit the answer to say that, and maybe a way for the OP to help if happen if you think they can.

              – user87779
              Apr 5 at 21:55















              @user87779: I don't suppose you could splice an edit in? I've ran out of ability (which is why my rep stays low...)

              – Joshua
              Apr 5 at 23:04





              @user87779: I don't suppose you could splice an edit in? I've ran out of ability (which is why my rep stays low...)

              – Joshua
              Apr 5 at 23:04













              huh, I'm not able to either. I wonder if the question was protected or something weird.

              – user87779
              Apr 6 at 0:34





              huh, I'm not able to either. I wonder if the question was protected or something weird.

              – user87779
              Apr 6 at 0:34











              0














              Other answers covered how to cover the financial side of the things. Now, if their damage also causes you unnecessary anxiety and setbacks that extra money alone can't fix, you can eliminate that damage alone. For example, with these measures:




              • Don't work on the same codebase. Only merge their changes occasionally (to drastically limit the time spent on pointing out their flaws again and again) and only after they pass your scrunity.


                • You can rationalize this to the client as smth like: "Their code is not up to our standards so we have to bring it up to them each time before incorporating it -- otherwise, it costs much more of our time and your money down the line".

                • Incentivise them to merge your changes back opportunistically by smth like: "Otherwise, it will cost us disproportionally more time on the next merge."

                • You mentioned that they are using SVN. You can use Git internally 'cuz it features much more advanced branching and merging logic, making complex merges much easier. (Git comes with a two-way SVN bridge out of the box.)



              • Don't fix their bugs for them as an integral part of your work but rather as a separate activity (e.g. as a part of the above-mentioned scrunity) so that it's easy to separate it from your regular work and easy to bill for it separately (plus the client will see exactly how much their staff's incompetence is costing them).

              • If your part of the work depends on some modules provided by them, warn the client that you will not complete that part of functionality if their module doesn't arrive in time. Only work on that module once the client explicitly asks you to and in the same manner as above.

              • Offer to coach their staff as an extra activity but only if they themselves are willing -- from code reviews (e.g. during the above scrunity, let them themselves address the flaws) to teaching them the best practices.






              share|improve this answer






























                0














                Other answers covered how to cover the financial side of the things. Now, if their damage also causes you unnecessary anxiety and setbacks that extra money alone can't fix, you can eliminate that damage alone. For example, with these measures:




                • Don't work on the same codebase. Only merge their changes occasionally (to drastically limit the time spent on pointing out their flaws again and again) and only after they pass your scrunity.


                  • You can rationalize this to the client as smth like: "Their code is not up to our standards so we have to bring it up to them each time before incorporating it -- otherwise, it costs much more of our time and your money down the line".

                  • Incentivise them to merge your changes back opportunistically by smth like: "Otherwise, it will cost us disproportionally more time on the next merge."

                  • You mentioned that they are using SVN. You can use Git internally 'cuz it features much more advanced branching and merging logic, making complex merges much easier. (Git comes with a two-way SVN bridge out of the box.)



                • Don't fix their bugs for them as an integral part of your work but rather as a separate activity (e.g. as a part of the above-mentioned scrunity) so that it's easy to separate it from your regular work and easy to bill for it separately (plus the client will see exactly how much their staff's incompetence is costing them).

                • If your part of the work depends on some modules provided by them, warn the client that you will not complete that part of functionality if their module doesn't arrive in time. Only work on that module once the client explicitly asks you to and in the same manner as above.

                • Offer to coach their staff as an extra activity but only if they themselves are willing -- from code reviews (e.g. during the above scrunity, let them themselves address the flaws) to teaching them the best practices.






                share|improve this answer




























                  0












                  0








                  0







                  Other answers covered how to cover the financial side of the things. Now, if their damage also causes you unnecessary anxiety and setbacks that extra money alone can't fix, you can eliminate that damage alone. For example, with these measures:




                  • Don't work on the same codebase. Only merge their changes occasionally (to drastically limit the time spent on pointing out their flaws again and again) and only after they pass your scrunity.


                    • You can rationalize this to the client as smth like: "Their code is not up to our standards so we have to bring it up to them each time before incorporating it -- otherwise, it costs much more of our time and your money down the line".

                    • Incentivise them to merge your changes back opportunistically by smth like: "Otherwise, it will cost us disproportionally more time on the next merge."

                    • You mentioned that they are using SVN. You can use Git internally 'cuz it features much more advanced branching and merging logic, making complex merges much easier. (Git comes with a two-way SVN bridge out of the box.)



                  • Don't fix their bugs for them as an integral part of your work but rather as a separate activity (e.g. as a part of the above-mentioned scrunity) so that it's easy to separate it from your regular work and easy to bill for it separately (plus the client will see exactly how much their staff's incompetence is costing them).

                  • If your part of the work depends on some modules provided by them, warn the client that you will not complete that part of functionality if their module doesn't arrive in time. Only work on that module once the client explicitly asks you to and in the same manner as above.

                  • Offer to coach their staff as an extra activity but only if they themselves are willing -- from code reviews (e.g. during the above scrunity, let them themselves address the flaws) to teaching them the best practices.






                  share|improve this answer















                  Other answers covered how to cover the financial side of the things. Now, if their damage also causes you unnecessary anxiety and setbacks that extra money alone can't fix, you can eliminate that damage alone. For example, with these measures:




                  • Don't work on the same codebase. Only merge their changes occasionally (to drastically limit the time spent on pointing out their flaws again and again) and only after they pass your scrunity.


                    • You can rationalize this to the client as smth like: "Their code is not up to our standards so we have to bring it up to them each time before incorporating it -- otherwise, it costs much more of our time and your money down the line".

                    • Incentivise them to merge your changes back opportunistically by smth like: "Otherwise, it will cost us disproportionally more time on the next merge."

                    • You mentioned that they are using SVN. You can use Git internally 'cuz it features much more advanced branching and merging logic, making complex merges much easier. (Git comes with a two-way SVN bridge out of the box.)



                  • Don't fix their bugs for them as an integral part of your work but rather as a separate activity (e.g. as a part of the above-mentioned scrunity) so that it's easy to separate it from your regular work and easy to bill for it separately (plus the client will see exactly how much their staff's incompetence is costing them).

                  • If your part of the work depends on some modules provided by them, warn the client that you will not complete that part of functionality if their module doesn't arrive in time. Only work on that module once the client explicitly asks you to and in the same manner as above.

                  • Offer to coach their staff as an extra activity but only if they themselves are willing -- from code reviews (e.g. during the above scrunity, let them themselves address the flaws) to teaching them the best practices.







                  share|improve this answer














                  share|improve this answer



                  share|improve this answer








                  edited 7 hours ago

























                  answered 2 days ago









                  ivan_pozdeevivan_pozdeev

                  31619




                  31619























                      -1














                      The customer (here: the client) is always right. As long as the customer pays. So as long as the customer pays for every hour you work, it doesn’t matter if their team is lazy and incompetent. If your job takes three times longer, you get paid three times as much.



                      Of course, as long as the customer pays. So you should have a log about anything you asked the client team to do, and when it was delivered, and with ho many bugs. So if the customer doesn’t want to pay, you can show them why things take so long.






                      share|improve this answer



















                      • 1





                        The OP has said they get a fixed amount of money. I don't know exactly what that entails, but in a few other comments they seem to imply they don't get paid more for working longer. That seems crazy to me, but you may know more about situations like that.

                        – user87779
                        Apr 5 at 22:27


















                      -1














                      The customer (here: the client) is always right. As long as the customer pays. So as long as the customer pays for every hour you work, it doesn’t matter if their team is lazy and incompetent. If your job takes three times longer, you get paid three times as much.



                      Of course, as long as the customer pays. So you should have a log about anything you asked the client team to do, and when it was delivered, and with ho many bugs. So if the customer doesn’t want to pay, you can show them why things take so long.






                      share|improve this answer



















                      • 1





                        The OP has said they get a fixed amount of money. I don't know exactly what that entails, but in a few other comments they seem to imply they don't get paid more for working longer. That seems crazy to me, but you may know more about situations like that.

                        – user87779
                        Apr 5 at 22:27
















                      -1












                      -1








                      -1







                      The customer (here: the client) is always right. As long as the customer pays. So as long as the customer pays for every hour you work, it doesn’t matter if their team is lazy and incompetent. If your job takes three times longer, you get paid three times as much.



                      Of course, as long as the customer pays. So you should have a log about anything you asked the client team to do, and when it was delivered, and with ho many bugs. So if the customer doesn’t want to pay, you can show them why things take so long.






                      share|improve this answer













                      The customer (here: the client) is always right. As long as the customer pays. So as long as the customer pays for every hour you work, it doesn’t matter if their team is lazy and incompetent. If your job takes three times longer, you get paid three times as much.



                      Of course, as long as the customer pays. So you should have a log about anything you asked the client team to do, and when it was delivered, and with ho many bugs. So if the customer doesn’t want to pay, you can show them why things take so long.







                      share|improve this answer












                      share|improve this answer



                      share|improve this answer










                      answered Apr 5 at 21:34









                      gnasher729gnasher729

                      91.1k41162286




                      91.1k41162286








                      • 1





                        The OP has said they get a fixed amount of money. I don't know exactly what that entails, but in a few other comments they seem to imply they don't get paid more for working longer. That seems crazy to me, but you may know more about situations like that.

                        – user87779
                        Apr 5 at 22:27
















                      • 1





                        The OP has said they get a fixed amount of money. I don't know exactly what that entails, but in a few other comments they seem to imply they don't get paid more for working longer. That seems crazy to me, but you may know more about situations like that.

                        – user87779
                        Apr 5 at 22:27










                      1




                      1





                      The OP has said they get a fixed amount of money. I don't know exactly what that entails, but in a few other comments they seem to imply they don't get paid more for working longer. That seems crazy to me, but you may know more about situations like that.

                      – user87779
                      Apr 5 at 22:27







                      The OP has said they get a fixed amount of money. I don't know exactly what that entails, but in a few other comments they seem to imply they don't get paid more for working longer. That seems crazy to me, but you may know more about situations like that.

                      – user87779
                      Apr 5 at 22:27







                      protected by mcknz yesterday



                      Thank you for your interest in this question.
                      Because it has attracted low-quality or spam answers that had to be removed, posting an answer now requires 10 reputation on this site (the association bonus does not count).



                      Would you like to answer one of these unanswered questions instead?



                      Popular posts from this blog

                      Færeyskur hestur Heimild | Tengill | Tilvísanir | LeiðsagnarvalRossið - síða um færeyska hrossið á færeyskuGott ár hjá færeyska hestinum

                      He _____ here since 1970 . Answer needed [closed]What does “since he was so high” mean?Meaning of “catch birds for”?How do I ensure “since” takes the meaning I want?“Who cares here” meaningWhat does “right round toward” mean?the time tense (had now been detected)What does the phrase “ring around the roses” mean here?Correct usage of “visited upon”Meaning of “foiled rail sabotage bid”It was the third time I had gone to Rome or It is the third time I had been to Rome

                      Slayer Innehåll Historia | Stil, komposition och lyrik | Bandets betydelse och framgångar | Sidoprojekt och samarbeten | Kontroverser | Medlemmar | Utmärkelser och nomineringar | Turnéer och festivaler | Diskografi | Referenser | Externa länkar | Navigeringsmenywww.slayer.net”Metal Massacre vol. 1””Metal Massacre vol. 3””Metal Massacre Volume III””Show No Mercy””Haunting the Chapel””Live Undead””Hell Awaits””Reign in Blood””Reign in Blood””Gold & Platinum – Reign in Blood””Golden Gods Awards Winners”originalet”Kerrang! Hall Of Fame””Slayer Looks Back On 37-Year Career In New Video Series: Part Two””South of Heaven””Gold & Platinum – South of Heaven””Seasons in the Abyss””Gold & Platinum - Seasons in the Abyss””Divine Intervention””Divine Intervention - Release group by Slayer””Gold & Platinum - Divine Intervention””Live Intrusion””Undisputed Attitude””Abolish Government/Superficial Love””Release “Slatanic Slaughter: A Tribute to Slayer” by Various Artists””Diabolus in Musica””Soundtrack to the Apocalypse””God Hates Us All””Systematic - Relationships””War at the Warfield””Gold & Platinum - War at the Warfield””Soundtrack to the Apocalypse””Gold & Platinum - Still Reigning””Metallica, Slayer, Iron Mauden Among Winners At Metal Hammer Awards””Eternal Pyre””Eternal Pyre - Slayer release group””Eternal Pyre””Metal Storm Awards 2006””Kerrang! Hall Of Fame””Slayer Wins 'Best Metal' Grammy Award””Slayer Guitarist Jeff Hanneman Dies””Bullet-For My Valentine booed at Metal Hammer Golden Gods Awards””Unholy Aliance””The End Of Slayer?””Slayer: We Could Thrash Out Two More Albums If We're Fast Enough...””'The Unholy Alliance: Chapter III' UK Dates Added”originalet”Megadeth And Slayer To Co-Headline 'Canadian Carnage' Trek”originalet”World Painted Blood””Release “World Painted Blood” by Slayer””Metallica Heading To Cinemas””Slayer, Megadeth To Join Forces For 'European Carnage' Tour - Dec. 18, 2010”originalet”Slayer's Hanneman Contracts Acute Infection; Band To Bring In Guest Guitarist””Cannibal Corpse's Pat O'Brien Will Step In As Slayer's Guest Guitarist”originalet”Slayer’s Jeff Hanneman Dead at 49””Dave Lombardo Says He Made Only $67,000 In 2011 While Touring With Slayer””Slayer: We Do Not Agree With Dave Lombardo's Substance Or Timeline Of Events””Slayer Welcomes Drummer Paul Bostaph Back To The Fold””Slayer Hope to Unveil Never-Before-Heard Jeff Hanneman Material on Next Album””Slayer Debut New Song 'Implode' During Surprise Golden Gods Appearance””Release group Repentless by Slayer””Repentless - Slayer - Credits””Slayer””Metal Storm Awards 2015””Slayer - to release comic book "Repentless #1"””Slayer To Release 'Repentless' 6.66" Vinyl Box Set””BREAKING NEWS: Slayer Announce Farewell Tour””Slayer Recruit Lamb of God, Anthrax, Behemoth + Testament for Final Tour””Slayer lägger ner efter 37 år””Slayer Announces Second North American Leg Of 'Final' Tour””Final World Tour””Slayer Announces Final European Tour With Lamb of God, Anthrax And Obituary””Slayer To Tour Europe With Lamb of God, Anthrax And Obituary””Slayer To Play 'Last French Show Ever' At Next Year's Hellfst””Slayer's Final World Tour Will Extend Into 2019””Death Angel's Rob Cavestany On Slayer's 'Farewell' Tour: 'Some Of Us Could See This Coming'””Testament Has No Plans To Retire Anytime Soon, Says Chuck Billy””Anthrax's Scott Ian On Slayer's 'Farewell' Tour Plans: 'I Was Surprised And I Wasn't Surprised'””Slayer””Slayer's Morbid Schlock””Review/Rock; For Slayer, the Mania Is the Message””Slayer - Biography””Slayer - Reign In Blood”originalet”Dave Lombardo””An exclusive oral history of Slayer”originalet”Exclusive! Interview With Slayer Guitarist Jeff Hanneman”originalet”Thinking Out Loud: Slayer's Kerry King on hair metal, Satan and being polite””Slayer Lyrics””Slayer - Biography””Most influential artists for extreme metal music””Slayer - Reign in Blood””Slayer guitarist Jeff Hanneman dies aged 49””Slatanic Slaughter: A Tribute to Slayer””Gateway to Hell: A Tribute to Slayer””Covered In Blood””Slayer: The Origins of Thrash in San Francisco, CA.””Why They Rule - #6 Slayer”originalet”Guitar World's 100 Greatest Heavy Metal Guitarists Of All Time”originalet”The fans have spoken: Slayer comes out on top in readers' polls”originalet”Tribute to Jeff Hanneman (1964-2013)””Lamb Of God Frontman: We Sound Like A Slayer Rip-Off””BEHEMOTH Frontman Pays Tribute To SLAYER's JEFF HANNEMAN””Slayer, Hatebreed Doing Double Duty On This Year's Ozzfest””System of a Down””Lacuna Coil’s Andrea Ferro Talks Influences, Skateboarding, Band Origins + More””Slayer - Reign in Blood””Into The Lungs of Hell””Slayer rules - en utställning om fans””Slayer and Their Fans Slashed Through a No-Holds-Barred Night at Gas Monkey””Home””Slayer””Gold & Platinum - The Big 4 Live from Sofia, Bulgaria””Exclusive! Interview With Slayer Guitarist Kerry King””2008-02-23: Wiltern, Los Angeles, CA, USA””Slayer's Kerry King To Perform With Megadeth Tonight! - Oct. 21, 2010”originalet”Dave Lombardo - Biography”Slayer Case DismissedArkiveradUltimate Classic Rock: Slayer guitarist Jeff Hanneman dead at 49.”Slayer: "We could never do any thing like Some Kind Of Monster..."””Cannibal Corpse'S Pat O'Brien Will Step In As Slayer'S Guest Guitarist | The Official Slayer Site”originalet”Slayer Wins 'Best Metal' Grammy Award””Slayer Guitarist Jeff Hanneman Dies””Kerrang! Awards 2006 Blog: Kerrang! Hall Of Fame””Kerrang! Awards 2013: Kerrang! Legend”originalet”Metallica, Slayer, Iron Maien Among Winners At Metal Hammer Awards””Metal Hammer Golden Gods Awards””Bullet For My Valentine Booed At Metal Hammer Golden Gods Awards””Metal Storm Awards 2006””Metal Storm Awards 2015””Slayer's Concert History””Slayer - Relationships””Slayer - Releases”Slayers officiella webbplatsSlayer på MusicBrainzOfficiell webbplatsSlayerSlayerr1373445760000 0001 1540 47353068615-5086262726cb13906545x(data)6033143kn20030215029